12464-12466 W PINNEY ST 91331

Certificate Information: 12464-12466 W PINNEY ST 91331

Application / Permit
24010-20000-00444
Plan Check / Job No.
B24VN01507
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: NEW 1-STORY (34'-5" x 23'-10") SINGLE FAMILY DWELLING PER SB9 TWO-UNIT DEVELOPMENT CA GOVT. CODE 65852.21 WITH AN ATTACHED (34'-5" x 23'-10") ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 9/25/2024
Issuing Office
Current Status
CofO Issued on 9/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 VAHAN JIVALAGIAN
Corrections Issued 2/27/2024 VAHAN JIVALAGIAN
Quality Review Completed 3/5/2024 OMID HEDAYAT
Applicant returned to address corrections 9/20/2024 VAHAN JIVALAGIAN
Plan Check Approved 9/24/2024 VAHAN JIVALAGIAN
Issued 9/25/2024 APPLICANT
CofO in Progress 9/9/2025 MICHEL ABAJAN
Permit Finaled 9/10/2025 RUBEN SALAS
CofO Issued 9/10/2025 RUBEN SALAS
Permit Finaled 9/10/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/14/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/14/2024 CARLOS AGUILERA
Sewer availability Cleared 3/14/2024 CARLOS AGUILERA
Clean Up Green Up Cleared 4/2/2024 BRENNEN OBETO
Senate Bill 9 Cleared 4/9/2024 BRENNEN OBETO
Hydrant and Access approval Cleared 5/3/2024 RUEL COLE
Low Impact Development (LID) Cleared 6/17/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/24/2024 CARLOS RAMIREZ
Construction near power lines Cleared 7/25/2024 RIDWAN HARDY
Miscellaneous Cleared 8/23/2024 GREGORIO GUILLERMO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/17/2024 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 12/24/2024 Approved MICHEL ABAJAN
Footing/Foundation/Slab 12/24/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 2/11/2025 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 2/11/2025 Approved MICHEL ABAJAN
Green Building Rough 2/11/2025 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 2/11/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 2/11/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 2/11/2025 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 2/25/2025 Approved MICHEL ABAJAN
Green Building Rough 2/25/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/25/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 2/25/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/26/2025 Approved MICHEL ABAJAN
Insulation 2/28/2025 Approved MICHEL ABAJAN
Sewer 2/28/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/24/2025 Approved MICHEL ABAJAN
Drywall Nailing 5/21/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/21/2025 Approved MICHEL ABAJAN
Final 5/21/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 5/21/2025 Approved MICHEL ABAJAN
HVAC-Final 5/21/2025 Approved MICHEL ABAJAN
PLUMBING-Final 5/21/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 5/21/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 5/21/2025 Approved MICHEL ABAJAN
Final 9/8/2025 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 9/8/2025 Approved MICHEL ABAJAN