17224 W KITTRIDGE ST 91406

Certificate Information: 17224 W KITTRIDGE ST 91406

Application / Permit
24010-20000-00438
Plan Check / Job No.
B23VN18029
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) DETACHED 748 SF ADU W/ATTACHED 160 SF TRELLIS. PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 6/11/2025
Issuing Office
Current Status
Issued on 6/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/16/2024 ALFREDO JARA
Corrections Issued 2/17/2024 ALFREDO JARA
Applicant returned to address corrections 3/19/2024 EDWIN ESPIN
Applicant returned to address corrections 9/25/2024 ALFREDO JARA
Applicant returned to address corrections 10/18/2024 ALFREDO JARA
Applicant returned to address corrections 11/20/2024 ALFREDO JARA
Applicant returned to address corrections 11/24/2024 ALFREDO JARA
Plan Check Approved 12/12/2024 JOHNPAUL ISIP
Issued 6/11/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/14/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/14/2024 LEE GUILBEAUX
Watercourse Cleared 3/14/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/14/2024 LEE GUILBEAUX
Sewer availability Cleared 4/8/2024 LEE GUILBEAUX
ZI Cleared 4/24/2024 NATHAN ROMINE
Construction near power lines Cleared 6/25/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 8/31/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/24/2024 RYAN CASTRO

Contact Information

Contractor I D B Enterprise Inc; Lic. No.: 1032682-B       ,
Engineer Ramos,, Victor; Lic. No.: C86568 4823 ALMAGUER AVE      GUADALUPE, CA 93434

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/22/2025 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 9/25/2025 Approved JON MCHUGH
PLUMBING-Rough 10/10/2025 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Partial Approval JON MCHUGH
PLUMBING-Rough 10/15/2025 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 10/22/2025 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 11/19/2025 Partial Approval JON MCHUGH
HVAC-Rough 2/18/2026 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 2/18/2026 Not Ready for Inspection JON MCHUGH
Rough-Elec/Plmb/HVAC 2/18/2026 Corrections Issued JON MCHUGH
Interior/Exterior Lathing 2/25/2026 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 3/5/2026 Corrections Issued JON MCHUGH
Insulation 3/5/2026 Approved JON MCHUGH
Drywall Nailing 3/13/2026 Not Ready for Inspection JON MCHUGH
Interior/Exterior Lathing 3/18/2026 Partial Approval JON MCHUGH
BUILDING-Rough-Frame 3/26/2026 Partial Approval MORRIS JACKSON
Drywall Nailing 3/26/2026 Approved MORRIS JACKSON
Green Building Rough 3/26/2026 Approved MORRIS JACKSON
Rough-Elec/Plmb/HVAC 3/26/2026 Approved MORRIS JACKSON
Verify Sprinkler Sign Off 3/26/2026 Partial Inspection MORRIS JACKSON
BUILDING-Rough-Frame 4/9/2026 Partial Approval MORRIS JACKSON
Interior/Exterior Lathing 4/9/2026 Approved MORRIS JACKSON
Sewer 5/6/2026 Approved JON MCHUGH