17508 W SEPTO ST 91325

Certificate Information: 17508 W SEPTO ST 91325

Application / Permit
24010-20000-00436
Plan Check / Job No.
B24VN01472
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New Detached Accessory Dwelling Unit at rear of the lot per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 6/17/2024
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2024 APPLICANT
Assigned to Plan Check Engineer 2/14/2024 EDWIN ESPIN
Corrections Issued 2/15/2024 EDWIN ESPIN
Applicant returned to address corrections 3/19/2024 CAROLEAN BASMA
Applicant returned to address corrections 3/29/2024 CAROLEAN BASMA
Plan Check Approved 6/17/2024 CAROLEAN BASMA
Issued 6/17/2024 APPLICANT
CofO in Progress 9/15/2025 CHRISTOPHER ROJAS
No Progress 9/19/2025 RAUL OLAGI
CofO in Progress 9/19/2025 RAUL OLAGI
CofO in Progress 9/22/2025 CHRISTOPHER ROJAS
CofO in Progress 11/7/2025 RAUL OLAGI
Permit Finaled 11/18/2025 RUBEN SALAS
CofO Issued 11/18/2025 RUBEN SALAS
Permit Finaled 11/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/11/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 3/11/2024 CARLOS RAMIREZ
Sewer availability Cleared 3/12/2024 CARLOS RAMIREZ
Low Impact Development (LID) Cleared 3/19/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 3/21/2024 CARLOS RAMIREZ
Construction near power lines Cleared 6/10/2024 RIDWAN HARDY

Contact Information

Contractor Maestro Construction Inc; Lic. No.: 1060987-B       ,
Engineer Xia,, Ji; Lic. No.: S7144 260 S LOS ROBLES AVE, STE 100      PASADENA, CA 91101

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/2/2024 Corrections Issued RAUL OLAGI
Special/Order Compliance 7/2/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 7/16/2024 Partial Inspection JAVIER RAMOS JR
Deputy Drilled-In Anchors 7/23/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 7/30/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 7/30/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 8/5/2024 Approved JAVIER RAMOS JR
Wood Frame 9/18/2024 Partial Approval JACK KARGODORIAN
Wood Frame 9/19/2024 No Access for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 10/18/2024 Approved JACK KARGODORIAN
HVAC-Rough 10/18/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 10/18/2024 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/22/2024 Approved JACK KARGODORIAN
Green Building Rough 10/22/2024 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 10/22/2024 Approved JACK KARGODORIAN
Wood Frame 10/22/2024 Approved JACK KARGODORIAN
Insulation 10/31/2024 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 10/31/2024 Partial Approval JACK KARGODORIAN
Shower Pan 10/31/2024 Not Ready for Inspection JACK KARGODORIAN
Insulation 11/19/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 11/19/2024 Approved LOUIS ESCOTO
Shower Pan 11/19/2024 Approved LOUIS ESCOTO
Drywall Nailing 11/22/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 11/22/2024 Not Ready for Inspection MICHAEL CORTEZ
Sewer 11/22/2024 Not Ready for Inspection MICHAEL CORTEZ
Sewer 11/27/2024 Approved LOUIS ESCOTO
ELECTRICAL-Final 3/18/2025 Approved JAVIER RAMOS JR
Final 3/18/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 3/18/2025 Approved JAVIER RAMOS JR
HVAC-Final 3/18/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 3/18/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/18/2025 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 3/18/2025 Approved JAVIER RAMOS JR
Final 5/13/2025 Partial Inspection KEVIN BERBERYAN
Service/Power Release 5/13/2025 Not Required KEVIN BERBERYAN
Final 9/11/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Special/Order Compliance 9/22/2025 Corrections Issued CHRISTOPHER ROJAS
Final 11/7/2025 OK to Issue CofO RAUL OLAGI