10124 N SHOSHONE AVE 91325

Certificate Information: 10124 N SHOSHONE AVE 91325

Application / Permit
24010-20000-00400
Plan Check / Job No.
B24VN01306
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 32'-6" X 43' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/18/2024
Issuing Office
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 SELLA BENYAMIN
Corrections Issued 2/22/2024 SELLA BENYAMIN
Quality Review Completed 2/23/2024 STEVEN KIM
Applicant returned to address corrections 8/16/2024 SELLA BENYAMIN
Plan Check Approved 10/18/2024 SELLA BENYAMIN
Issued 10/18/2024 APPLICANT
CofO in Progress 9/24/2025 CHRISTOPHER ROJAS
Permit Finaled 10/14/2025 RUBEN SALAS
CofO Issued 10/14/2025 RUBEN SALAS
Permit Finaled 10/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/9/2024 CARLOS AGUILERA
Construction near power lines Cleared 4/9/2024 WALTER RAMIREZ
Low Impact Development (LID) Cleared 7/8/2024 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 7/29/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/29/2024 CARLOS AGUILERA
Sewer availability Cleared 7/29/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/18/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 11/21/2024 Corrections Issued JAVIER RAMOS JR
Wood Frame 12/20/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 12/27/2024 Approved JAVIER RAMOS JR
Wood Frame 12/27/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 2/10/2025 Approved MATTHEW NELSON
ELECTRICAL-Rough 2/10/2025 Approved MATTHEW NELSON
Green Building Rough 2/10/2025 Approved MATTHEW NELSON
HVAC-Rough 2/10/2025 Approved MATTHEW NELSON
PLUMBING-Rough 2/10/2025 Approved MATTHEW NELSON
Shower Pan 2/10/2025 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 2/10/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/12/2025 Approved LOUIS ESCOTO
Shower Pan 2/12/2025 Approved LOUIS ESCOTO
Drywall Nailing 2/20/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/7/2025 Approved JAVIER RAMOS JR
Final 4/30/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 4/30/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Not Required CHRISTOPHER ROJAS
Service/Power Release 4/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 4/30/2025 Approved CHRISTOPHER ROJAS
Final 5/14/2025 Corrections Issued CHRISTOPHER ROJAS
Service/Power Release 5/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 9/24/2025 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 9/24/2025 Approved CHRISTOPHER ROJAS