10124 N SHOSHONE AVE 91325
Certificate Information: 10124 N SHOSHONE AVE 91325
- Application / Permit
- 24010-20000-00400
- Plan Check / Job No.
- B24VN01306
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW 32'-6" X 43' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/18/2024
- Issuing Office
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | SELLA BENYAMIN |
| Corrections Issued | 2/22/2024 | SELLA BENYAMIN |
| Quality Review Completed | 2/23/2024 | STEVEN KIM |
| Applicant returned to address corrections | 8/16/2024 | SELLA BENYAMIN |
| Plan Check Approved | 10/18/2024 | SELLA BENYAMIN |
| Issued | 10/18/2024 | APPLICANT |
| CofO in Progress | 9/24/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
| CofO Issued | 10/14/2025 | RUBEN SALAS |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 4/9/2024 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 7/8/2024 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/29/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/29/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/18/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/21/2024 | Corrections Issued | JAVIER RAMOS JR |
| Wood Frame | 12/20/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/27/2024 | Approved | JAVIER RAMOS JR |
| Wood Frame | 12/27/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/10/2025 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/10/2025 | Approved | MATTHEW NELSON |
| Green Building Rough | 2/10/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 2/10/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/10/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 2/10/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 2/10/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/12/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 2/12/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 2/20/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/7/2025 | Approved | JAVIER RAMOS JR |
| Final | 4/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 4/30/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV Not Required | CHRISTOPHER ROJAS |
| Service/Power Release | 4/30/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 4/30/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 5/14/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Service/Power Release | 5/14/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 9/24/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 9/24/2025 | Approved | CHRISTOPHER ROJAS |