18110 W GAULT ST 91335
Certificate Information: 18110 W GAULT ST 91335
- Application / Permit
- 24010-20000-00367
- Plan Check / Job No.
- B24VN01194
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28'-6" x 30'-3" ONE-STORY DET. ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33 (c)-(d)]; NFPA 13D THRU-OUT
- Permit Issued
- Issued on 12/19/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2024 | SEAN SHAHMIRI |
| Corrections Issued | 2/14/2024 | SEAN SHAHMIRI |
| Quality Review Completed | 2/15/2024 | STEVEN KIM |
| Building Plans Picked Up | 2/29/2024 | APPLICANT |
| Applicant returned to address corrections | 9/25/2024 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 12/12/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 12/12/2024 | SEAN SHAHMIRI |
| Issued | 12/19/2024 | APPLICANT |
| CofO in Progress | 11/4/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 11/7/2025 | JOHN JANSON |
| CofO Issued | 11/7/2025 | JOHN JANSON |
| Permit Finaled | 11/7/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/8/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 12/4/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/9/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 375 LA MIRADA AVENUE SAN MARINO, CA 91108 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 4/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 4/21/2025 | Partial Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 4/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 4/24/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/24/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 5/1/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/1/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 5/1/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 5/1/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/1/2025 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 5/1/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 5/6/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 5/9/2025 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 5/9/2025 | Partial Approval | HENRY KIM |
| Smoke Detectors | 5/9/2025 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 6/13/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 6/13/2025 | Approved | ARUTYUN MADATYAN |
| Final | 7/18/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 7/18/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 7/18/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 7/18/2025 | Approved | ARUTYUN MADATYAN |
| Final | 8/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 8/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Service/Power Release | 8/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 9/15/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 9/15/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 9/15/2025 | Approved | ARUTYUN MADATYAN |
| Final | 10/20/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 11/3/2025 | Approved | ARUTYUN MADATYAN |
| Final | 11/3/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 11/3/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 11/3/2025 | Approved | ARUTYUN MADATYAN |