8658 N SYLMAR AVE 91402

Certificate Information: 8658 N SYLMAR AVE 91402

Application / Permit
24010-20000-00317
Plan Check / Job No.
B24VN01040
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New two stories irregular shaped 24' 2" x 27' 3" ADU per LAMC 12.22 A.33(b)(1)3. All work done per engineer.
Permit Issued
Issued on 1/23/2025
Issuing Office
Current Status
CofO Issued on 8/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2024 APPLICANT
Assigned to Plan Check Engineer 1/29/2024 JEROME MAGAT PALMA
Corrections Issued 1/30/2024 JEROME MAGAT PALMA
Building Plans Picked Up 2/1/2024 APPLICANT
Applicant returned to address corrections 1/17/2025 NAREG ATARIAN
Applicant returned to address corrections 1/22/2025 NAREG ATARIAN
Plan Check Approved 1/23/2025 NAREG ATARIAN
Issued 1/23/2025 APPLICANT
CofO in Progress 8/8/2025 VINCENT HANLEY
Permit Finaled 8/26/2025 RUBEN SALAS
CofO Issued 8/26/2025 RUBEN SALAS
Permit Finaled 8/26/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/1/2024 CARLOS RAMIREZ
Low Impact Development (LID) Cleared 10/30/2024 MITESH PATEL
Construction near power lines Cleared 1/14/2025 EDGAR PASCUA
Construction within easement Cleared 1/14/2025 EDGAR PASCUA
Roof/Waste drainage to street Cleared 1/17/2025 KIMBERLY HERNANDEZ
Sewer availability Cleared 1/17/2025 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 1/22/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/20/2025 Partial Approval VINCENT HANLEY
Deputy Wood Construction 3/27/2025 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/17/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 4/17/2025 Approved VINCENT HANLEY
Green Building Rough 4/17/2025 Approved VINCENT HANLEY
HVAC-Rough 4/17/2025 Approved VINCENT HANLEY
PLUMBING-Rough 4/17/2025 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 4/17/2025 Not Ready for Inspection VINCENT HANLEY
Wood Frame 4/17/2025 Approved VINCENT HANLEY
Insulation 4/28/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/2/2025 Approved VINCENT HANLEY
Drywall Nailing 5/2/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/13/2025 Approved JACK KARGODORIAN
Sewer 6/17/2025 Approved VINCENT HANLEY
Underground Mechanical 6/17/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 8/5/2025 Approved VINCENT HANLEY
Final 8/5/2025 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 8/5/2025 Approved VINCENT HANLEY
Green Building Final 8/5/2025 Approved VINCENT HANLEY
HVAC-Final 8/5/2025 Approved VINCENT HANLEY
PLUMBING-Final 8/5/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/5/2025 SGSOV Not Required VINCENT HANLEY
Service/Power Release 8/5/2025 Approved VINCENT HANLEY
Smoke Detectors 8/5/2025 Approved VINCENT HANLEY
Final 8/8/2025 OK to Issue CofO VINCENT HANLEY