6350 N WOODLAKE AVE 91367
Certificate Information: 6350 N WOODLAKE AVE 91367
- Application / Permit
- 24010-20000-00218
- Plan Check / Job No.
- B24VN00754
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New detached ADU per state law
- Permit Issued
- Issued on 3/4/2024
- Issuing Office
- Current Status
- CofO Issued on 8/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2024 | MINA HABILI |
| Corrections Issued | 1/25/2024 | MINA HABILI |
| Plan Check Approved | 3/2/2024 | MINA HABILI |
| Issued | 3/4/2024 | APPLICANT |
| CofO in Progress | 8/23/2024 | JEFFREY HARTLINE |
| Permit Finaled | 8/27/2024 | JOHN JANSON |
| CofO Issued | 8/27/2024 | JOHN JANSON |
| Permit Finaled | 8/27/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/9/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/9/2024 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 2/20/2024 | CHARLES POWELL |
| Low Impact Development (LID) | Cleared | 2/28/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 2/29/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Sunset Home Builders Inc; Lic. No.: 1094054-B | , |
| Engineer | Kaballo,, Amir; Lic. No.: C90707 | 152 S SWALL DR BEVERLY HILLS, CA 90211 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/12/2024 | Approved | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/13/2024 | Approved | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 3/13/2024 | Approved | GEVORK IPCHYAN |
| Sewer | 3/13/2024 | Approved | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/14/2024 | No Access for Inspection | GEVORK IPCHYAN |
| Underground Mechanical | 3/15/2024 | Partial Approval | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/19/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Grounding or Bonding | 3/19/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/21/2024 | Partial Approval | GEVORK IPCHYAN |
| Grounding or Bonding | 3/21/2024 | Partial Approval | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 4/9/2024 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 4/9/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/9/2024 | Partial Approval | GEVORK IPCHYAN |
| Rough-Elec/Plmb/HVAC | 4/9/2024 | Approved | GEVORK IPCHYAN |
| Verify Sprinkler Sign Off | 4/9/2024 | Approved | GEVORK IPCHYAN |
| Insulation | 4/11/2024 | Partial Approval | GEVORK IPCHYAN |
| Shower Pan | 4/11/2024 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 4/15/2024 | Approved | GEVORK IPCHYAN |
| Gas Test | 4/15/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/15/2024 | Approved | GEVORK IPCHYAN |
| Service/Power Release | 5/17/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Service/Power Release | 5/21/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 7/10/2024 | Approved | GEVORK IPCHYAN |
| Final | 7/10/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 7/10/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 7/10/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 7/10/2024 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 7/10/2024 | Approved | GEVORK IPCHYAN |
| Final | 8/16/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 8/22/2024 | OK to Issue CofO | JEFFREY HARTLINE |