9317 N NAGLE AVE 91331
Certificate Information: 9317 N NAGLE AVE 91331
- Application / Permit
- 24010-20000-00211
- Plan Check / Job No.
- B24VN00737
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRR. SHAPED 30'-10" x 14'-9" TWO-STORY ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33 (c)-(d)]
- Permit Issued
- Issued on 4/29/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | SEAN SHAHMIRI |
| Corrections Issued | 1/30/2024 | SEAN SHAHMIRI |
| Quality Review Completed | 1/30/2024 | STEVEN KIM |
| Building Plans Picked Up | 1/30/2024 | APPLICANT |
| Plan Check Approved | 4/29/2024 | SEAN SHAHMIRI |
| Issued | 4/29/2024 | APPLICANT |
| CofO in Progress | 10/22/2025 | VINCENT HANLEY |
| CofO Issued | 11/14/2025 | RUBEN SALAS |
| Permit Finaled | 11/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2024 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 2/6/2024 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 3/5/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 3/6/2024 | CARLOS RAMIREZ |
| Construction within easement | Cleared | 4/10/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/11/2024 | Partial Approval | GREGG CUMMINGS |
| Sewer | 6/11/2024 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 6/11/2024 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 6/28/2024 | No Access for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 6/28/2024 | No Access for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/2/2024 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/2/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/5/2024 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/10/2024 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/10/2024 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/29/2024 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 8/29/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 8/29/2024 | Corrections Issued | DAVID ANDERSON |
| Special/Order Compliance | 8/29/2024 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/24/2024 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/24/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 9/24/2024 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 9/24/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 9/24/2024 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 9/24/2024 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/27/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/27/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 9/27/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 9/27/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 9/27/2024 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 9/27/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/24/2024 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/5/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/5/2024 | Partial Approval | GREGG CUMMINGS |
| Insulation | 11/13/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/13/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 11/13/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 11/25/2024 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 12/6/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/18/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/18/2025 | Approved | VINCENT HANLEY |
| Final | 6/18/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 6/18/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 6/18/2025 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 6/18/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Not Required | VINCENT HANLEY |
| Service/Power Release | 6/18/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 6/18/2025 | Approved | VINCENT HANLEY |
| Final | 10/21/2025 | OK to Issue CofO | VINCENT HANLEY |