19441 W HEMMINGWAY ST 91335
Certificate Information: 19441 W HEMMINGWAY ST 91335
- Application / Permit
- 24010-20000-00185
- Plan Check / Job No.
- B23VN17994
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW FULLY ELECTRIC, DETACHED 11'10" X 33'9" ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (e). WORK DONE PER WFPP DESIGN.
- Permit Issued
- Issued on 8/28/2024
- Issuing Office
- Current Status
- CofO Issued on 2/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2024 | MADISON ODELL |
| Corrections Issued | 1/24/2024 | MADISON ODELL |
| Applicant returned to address corrections | 4/13/2024 | MADISON ODELL |
| Plan Check Approved | 4/18/2024 | MADISON O'DELL |
| Issued | 8/28/2024 | APPLICANT |
| CofO in Progress | 1/17/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 2/26/2025 | JOHN JANSON |
| Permit Finaled | 2/26/2025 | JOHN JANSON |
| CofO Issued | 2/26/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/27/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/5/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 4/1/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/1/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Dotz Inc; Lic. No.: 1033830-B | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/26/2024 | Approved | JEFFREY BULL |
| Underground Mechanical | 9/26/2024 | Partial Approval | JEFFREY BULL |
| Deputy Drilled-In Anchors | 10/4/2024 | Conditional Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 10/7/2024 | Approved | JEFFREY BULL |
| Reinforced Concrete Frame | 10/7/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 10/31/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 10/31/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 10/31/2024 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 11/5/2024 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 11/5/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 11/8/2024 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 11/12/2024 | Conditional Approval | KRISTEN CAUSEY |
| Shower Pan | 11/12/2024 | Approved | KRISTEN CAUSEY |
| Insulation | 11/14/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 11/14/2024 | Partial Approval | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 11/15/2024 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 11/21/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 1/10/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 1/10/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 1/10/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 1/10/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 1/10/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 1/10/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 1/10/2025 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 1/10/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 1/16/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 1/16/2025 | Approved | ARUTYUN MADATYAN |
| Final | 1/16/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 1/16/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 1/16/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 1/16/2025 | Approved | ARUTYUN MADATYAN |