5741 N SIMPSON AVE 91607

Certificate Information: 5741 N SIMPSON AVE 91607

Application / Permit
24010-20000-00147
Plan Check / Job No.
B24VN00464
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32' X 22'10-1/2" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d), ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/1/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2024 APPLICANT
Assigned to Plan Check Engineer 2/1/2024 SELLA BENYAMIN
Corrections Issued 2/9/2024 SELLA BENYAMIN
Quality Review Completed 2/9/2024 STEVEN KIM
Building Plans Picked Up 2/12/2024 APPLICANT
Plan Check Approved 5/16/2024 SELLA BENYAMIN
Issued 7/1/2024 APPLICANT
CofO in Progress 8/22/2025 JOSE AVILA
CofO in Progress 10/23/2025 JOSE AVILA
Permit Finaled 11/19/2025 RUBEN SALAS
CofO Issued 11/19/2025 RUBEN SALAS
Permit Finaled 11/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/13/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/13/2024 CARLOS RAMIREZ
Sewer availability Cleared 2/13/2024 CARLOS RAMIREZ
Construction near power lines Cleared 3/29/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 4/23/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 4/23/2024 CARLOS RAMIREZ

Contact Information

Contractor Da Only Inc; Lic. No.: 1073836-B 9320 S LA CIENEGA BLVD      INGLEWOOD, CA 90301
Engineer Boranian,, Paul; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 10/1/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 10/1/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 10/11/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Corrections Issued JOSE AVILA
Rough-Elec/Plmb/HVAC 12/11/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 12/13/2024 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 12/18/2024 Conditional Approval JOSE AVILA
Green Building Rough 12/18/2024 Approved JOSE AVILA
Insulation 1/8/2025 Approved JOSE AVILA
Interior/Exterior Lathing 1/8/2025 Approved JOSE AVILA
Drywall Nailing 1/13/2025 Approved MISAEL ESPARZA
Shower Pan 2/13/2025 Approved JOSE AVILA
Interior/Exterior Lathing 2/24/2025 Approved MICHAEL CORTEZ
Rough-Elec/Plmb/HVAC 3/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Sewer 3/28/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/11/2025 Partial Inspection JOSE AVILA
Final 8/11/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 8/11/2025 Approved JOSE AVILA
Green Building Final 8/11/2025 Approved JOSE AVILA
MERV13>=Final 8/11/2025 Approved JOSE AVILA
MERV13>=Rough 8/11/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/11/2025 SGSOV Not Required JOSE AVILA
Service/Power Release 8/11/2025 Approved JOSE AVILA
Smoke Detectors 8/11/2025 Approved JOSE AVILA
Verify Sprinkler Sign Off 8/11/2025 Partial Inspection JOSE AVILA
Special/Order Compliance 8/13/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 8/20/2025 Approved JOSE AVILA
Final 8/20/2025 OK to Issue CofO JOSE AVILA
Green Building Rough 8/20/2025 Approved JOSE AVILA