8433 N RINCON AVE 91352
Certificate Information: 8433 N RINCON AVE 91352
- Application / Permit
- 24010-20000-00137
- Plan Check / Job No.
- B24VN00431
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) Detached 2-story ADU per ordinance (LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 3/25/2025
- Issuing Office
- Current Status
- CofO Issued on 11/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 2/16/2024 | HOOMAN HAJIZADEH |
| Quality Review Completed | 2/28/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 11/19/2024 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 2/21/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 3/20/2025 | HOOMAN HAJIZADEH |
| Issued | 3/25/2025 | APPLICANT |
| CofO in Progress | 10/15/2025 | MATTHEW NELSON |
| CofO Issued | 11/14/2025 | RUBEN SALAS |
| Permit Finaled | 11/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/5/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 8/7/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 8/8/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 10/3/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 1/6/2025 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/14/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/25/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Sewer | 4/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 5/1/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/9/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Green Building Rough | 5/9/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 5/9/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/20/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 5/20/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 5/20/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/28/2025 | Partial Inspection | MICHEL ABAJAN |
| Green Building Rough | 5/28/2025 | Partial Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/28/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/4/2025 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/18/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 6/18/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/18/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 6/18/2025 | Approved | MATTHEW NELSON |
| Green Building Rough | 6/24/2025 | Approved | MATTHEW NELSON |
| Insulation | 6/24/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/27/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 6/27/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 7/8/2025 | Approved | MATTHEW NELSON |
| Final | 9/25/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 9/25/2025 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/25/2025 | SGSOV Not Required | MATTHEW NELSON |
| Service/Power Release | 9/25/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 9/25/2025 | Approved | MATTHEW NELSON |
| Final | 10/14/2025 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 10/14/2025 | Approved | MATTHEW NELSON |
| Service/Power Release | 10/14/2025 | Approved | MATTHEW NELSON |