6113 N MELVIN AVE 91356
Certificate Information: 6113 N MELVIN AVE 91356
- Application / Permit
- 24010-20000-00104
- Plan Check / Job No.
- B24VN00314
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 29' X 50'-6" ONE STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g) WITH ATTACHED TRELLIS ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 4/5/2024
- Issuing Office
- Current Status
- Issued on 4/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 1/17/2024 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 1/17/2024 | STEVEN KIM |
| Building Plans Picked Up | 1/17/2024 | APPLICANT |
| Applicant returned to address corrections | 2/29/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 4/1/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 4/1/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/5/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/22/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 2/13/2024 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 2/27/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 2/27/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2024 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/11/2024 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 10/17/2024 | Corrections Issued | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 10/29/2024 | Partial Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 11/4/2024 | Conditional Approval | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 11/6/2024 | Partial Approval | JON MCHUGH |
| Special/Order Compliance | 11/6/2024 | Corrections Issued | JON MCHUGH |
| Deputy Reinf. Concrete | 11/7/2024 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 6/16/2025 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 6/16/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 6/16/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 6/20/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 6/20/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 6/20/2025 | Approved | JON MCHUGH |
| Wood Frame | 6/20/2025 | Partial Approval | JON MCHUGH |
| Insulation | 6/27/2025 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 6/27/2025 | Not Ready for Inspection | JON MCHUGH |
| Shower Pan | 7/21/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 7/25/2025 | Approved | JON MCHUGH |
| Green Building Rough | 7/25/2025 | Approved | JON MCHUGH |
| Insulation | 7/25/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 7/25/2025 | Not Ready for Inspection | JON MCHUGH |
| Verify Sprinkler Sign Off | 7/25/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 8/26/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 8/26/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 8/28/2025 | Approved | JON MCHUGH |