6115 N MELVIN AVE 91356

Certificate Information: 6115 N MELVIN AVE 91356

Application / Permit
24010-20000-00103
Plan Check / Job No.
B24VN00314
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 129' X 49'-6" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE AND PATIO COVER/ TRELLIS ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 4/5/2024
Issuing Office
Current Status
Issued on 4/5/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/9/2024 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 1/17/2024 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 1/17/2024 STEVEN KIM
Building Plans Picked Up 1/17/2024 APPLICANT
Applicant returned to address corrections 2/29/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 4/1/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 4/2/2024 SEWADA ZADOORAN MILAGARDI
Issued 4/5/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/22/2024 CARLOS AGUILERA
Sewer availability Cleared 1/22/2024 CARLOS AGUILERA
Miscellaneous Cleared 2/1/2024 ASHLEY RODARTE
Trees in Parkway Cleared 2/6/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 2/13/2024 LAVEON RIDER
Low Impact Development (LID) Cleared 2/27/2024 TOMMY YIN
Permit Cleared 2/27/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 2/27/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/28/2024 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/10/2024 Not Ready for Inspection JON MCHUGH
Footing/Foundation/Slab 10/17/2024 Not Ready for Inspection JON MCHUGH
Sewer 11/7/2024 Approved JON MCHUGH
Underground Mechanical 11/7/2024 Partial Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 11/19/2024 Approved JON MCHUGH
Deputy Reinf. Concrete 11/21/2024 Conditional Approval JON MCHUGH
Deputy Steel/Welding 11/25/2024 Conditional Approval JON MCHUGH
Deputy Drilled-In Anchors 12/2/2024 Conditional Approval HENRY KIM
Footing/Foundation/Slab 12/9/2024 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 1/9/2025 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 2/5/2025 No Access for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval JON MCHUGH
Deputy Wood Construction 4/23/2025 Conditional Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Partial Approval JON MCHUGH
Underground Mechanical 5/2/2025 Partial Approval JON MCHUGH
BUILDING-Rough-Frame 5/15/2025 Corrections Issued JON MCHUGH
PLUMBING-Rough 5/15/2025 Partial Approval JON MCHUGH
ELECTRICAL-Rough 5/16/2025 Corrections Issued JON MCHUGH
HVAC-Rough 5/23/2025 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 6/12/2025 Not Ready for Inspection JON MCHUGH
HVAC-Rough 6/12/2025 Not Ready for Inspection JON MCHUGH
Insulation 6/12/2025 Partial Approval JON MCHUGH
PLUMBING-Rough 6/12/2025 Approved JON MCHUGH
Wood Frame 6/12/2025 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Not Ready for Inspection JOHN COLEMAN
Wood Frame 6/17/2025 Not Ready for Inspection JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 6/20/2025 Partial Approval JON MCHUGH
Rough-Elec/Plmb/HVAC 6/20/2025 Approved JON MCHUGH
Wood Frame 6/20/2025 Approved JON MCHUGH
Gas Test 6/27/2025 Partial Approval JON MCHUGH
Insulation 6/27/2025 Partial Approval JON MCHUGH
Interior/Exterior Lathing 6/27/2025 Not Ready for Inspection JON MCHUGH
Shower Pan 7/21/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 7/25/2025 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Approved JON MCHUGH
Green Building Rough 7/25/2025 Approved JON MCHUGH
Insulation 7/25/2025 Approved JON MCHUGH
Interior/Exterior Lathing 7/25/2025 Not Ready for Inspection JON MCHUGH
Verify Sprinkler Sign Off 7/25/2025 Approved JON MCHUGH
Interior/Exterior Lathing 8/26/2025 Partial Approval JON MCHUGH
Interior/Exterior Lathing 8/28/2025 Approved JON MCHUGH
Drywall Nailing 9/3/2025 Approved MORRIS JACKSON
ELECTRICAL-Final 3/26/2026 Not Ready for Inspection MORRIS JACKSON
Service/Power Release 4/1/2026 Approved JON MCHUGH
Gas Test 5/12/2026 Partial Approval JON MCHUGH
SGSOV-Seismic Gas S/O Valve 5/12/2026 SGSOV Not Ready JON MCHUGH
Underground Mechanical 5/12/2026 Partial Approval JON MCHUGH