9655 N LARAMIE AVE 91311

Certificate Information: 9655 N LARAMIE AVE 91311

Application / Permit
24010-20000-00095
Plan Check / Job No.
B24VN00284
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New detached two story 21' 6" x 28' ADU per LAMC 12.22 A.33 (c)-(d). All work done per engineer.
Permit Issued
Issued on 4/30/2025
Issuing Office
Current Status
Issued on 4/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/9/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 NAREG ATARIAN
Corrections Issued 1/26/2024 NAREG ATARIAN
Quality Review Completed 1/29/2024 OMID HEDAYAT
Applicant returned to address corrections 3/14/2024 NAREG ATARIAN
Applicant returned to address corrections 4/25/2024 NAREG ATARIAN
Applicant returned to address corrections 4/24/2025 NAREG ATARIAN
Plan Check Approved 4/30/2025 NAREG ATARIAN
Issued 4/30/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/22/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 4/14/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 4/18/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/22/2025 CARLOS AGUILERA
Sewer availability Cleared 4/22/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Armando; Lic. No.: C83911 2000 W LINCOLN AVE      MONTEBELLO, CA 90640

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/2/2025 Partial Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 6/4/2025 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 6/4/2025 Partial Approval DAVID SCANTLIN
Sewer 6/4/2025 Approved DAVID SCANTLIN
Footing/Foundation/Slab 6/17/2025 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Partial Approval KRISTEN CAUSEY
Underground Mechanical 7/29/2025 Partial Approval KRISTEN CAUSEY
Verify Sprinkler Sign Off 7/29/2025 Partial Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 9/4/2025 Not Ready for Inspection KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Approved KRISTEN CAUSEY
Green Building Rough 9/4/2025 Not Ready for Inspection KRISTEN CAUSEY
Verify Sprinkler Sign Off 9/4/2025 Not Ready for Inspection KRISTEN CAUSEY
Wood Frame 9/4/2025 Partial Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 9/25/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 9/25/2025 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Approved KRISTEN CAUSEY
Green Building Rough 9/25/2025 Approved KRISTEN CAUSEY
HVAC-Rough 9/25/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 9/25/2025 Partial Approval KRISTEN CAUSEY
PLUMBING-Rough 9/25/2025 Approved KRISTEN CAUSEY
Verify Sprinkler Sign Off 9/25/2025 Partial Inspection KRISTEN CAUSEY
Wood Frame 9/25/2025 Partial Inspection KRISTEN CAUSEY
Drywall Nailing 10/7/2025 Conditional Approval SCOTT SOBEL
Insulation 10/7/2025 Approved SCOTT SOBEL
Shower Pan 10/29/2025 Approved KRISTEN CAUSEY