6127-6129 N AUCKLAND AVE 91606
Certificate Information: 6127-6129 N AUCKLAND AVE 91606
- Application / Permit
- 24010-20000-00068
- Plan Check / Job No.
- B24VN00195
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- TWO (N) DETACHED 2-STORY ACCESSORY DWELLING UNITS PER GCS65852.2(e)(1)(D) & LAMC 12.22 A.33(c)(d)(g) **ePlan**
- Permit Issued
- Issued on 9/13/2024
- Issuing Office
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/7/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/14/2024 | JASON HEALEY |
| Applicant returned to address corrections | 8/21/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/5/2024 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/12/2024 | NILOOFAR MEHRAIN |
| Issued | 9/13/2024 | APPLICANT |
| CofO in Progress | 3/25/2026 | ROBERTO PALACIOS-LOPEZ |
| CofO Issued | 4/9/2026 | RUBEN SALAS |
| Permit Finaled | 4/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2024 | KENIA CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2024 | KENIA CASTILLO |
| Hydrant and Access approval | Cleared | 5/1/2024 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 6/12/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 7/31/2024 | KENIA CASTILLO |
| Sewer availability | Cleared | 7/31/2024 | KENIA CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Keshishian,, Nejdeh Erik; Lic. No.: C38341 | 2654 RISA DR GLENDALE, CA 91208 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/7/2024 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 11/18/2024 | Corrections Issued | JOSE AVILA |
| Sewer | 11/18/2024 | Approved | JOSE AVILA |
| Underground Mechanical | 11/18/2024 | Corrections Issued | JOSE AVILA |
| Special/Order Compliance | 11/21/2024 | Approved | JOSE AVILA |
| Special/Order Compliance | 11/21/2024 | Partial Inspection | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/19/2025 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 3/19/2025 | Approved | JOSE AVILA |
| Deputy Wood Construction | 4/2/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2025 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 7/18/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/18/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/28/2025 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 7/28/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 7/28/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/12/2025 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 8/12/2025 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 8/12/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 8/15/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 8/15/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/20/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 9/2/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 9/2/2025 | Approved | JOSE AVILA |
| Shower Pan | 9/2/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/11/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 3/11/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV No Gas | GAREN HAYRAPETYAN |
| Service/Power Release | 3/11/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 3/11/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 3/24/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 3/24/2026 | Approved | ROBERTO PALACIOS-LOPEZ |