13286 N PHILLIPPI AVE 91342

Certificate Information: 13286 N PHILLIPPI AVE 91342

Application / Permit
24010-20000-00065
Plan Check / Job No.
B24VN00174
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached accessory dwelling unit with attached garage per LAMC 12.22 A.33 (c)-(d). Work per engineer details. **ePLAN**
Permit Issued
Issued on 9/14/2024
Issuing Office
Current Status
Issued on 9/14/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/5/2024 APPLICANT
Assigned to Plan Check Engineer 1/10/2024 VICTOR CHEN
Corrections Issued 1/11/2024 VICTOR CHEN
Applicant returned to address corrections 3/19/2024 NEHEMIAS RAMOS
Plan Check Approved 3/21/2024 JOSEPH RAFOLS
Plan Check Approved 9/11/2024 JOSEPH RAFOLS
Issued 9/14/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/13/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/16/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/16/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 3/6/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 3/6/2024 EDGAR ALCARAZ
Hydrant and Access approval Cleared 3/11/2024 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/20/2024 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 12/9/2024 Approved KEVIN BERBERYAN
Deputy Steel/Welding 1/16/2025 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 1/29/2025 Conditional Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 2/24/2025 Partial Inspection KEVIN BERBERYAN
ELECTRICAL-Rough 2/24/2025 Approved KEVIN BERBERYAN
Deputy Wood Construction 4/1/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 4/7/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/7/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/7/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/17/2025 Corrections Issued KEVIN BERBERYAN
Green Building Rough 4/17/2025 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Rough 4/17/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 4/17/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 4/24/2025 Approved KEVIN BERBERYAN
HVAC-Rough 5/12/2025 Approved KEVIN BERBERYAN
Insulation 5/12/2025 Approved KEVIN BERBERYAN
Drywall Nailing 5/27/2025 Approved KEVIN BERBERYAN
Shower Pan 8/11/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 8/21/2025 Approved LOUIS ESCOTO