13286 N PHILLIPPI AVE 91342
Certificate Information: 13286 N PHILLIPPI AVE 91342
- Application / Permit
- 24010-20000-00065
- Plan Check / Job No.
- B24VN00174
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached accessory dwelling unit with attached garage per LAMC 12.22 A.33 (c)-(d). Work per engineer details. **ePLAN**
- Permit Issued
- Issued on 9/14/2024
- Issuing Office
- Current Status
- Issued on 9/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2024 | VICTOR CHEN |
| Corrections Issued | 1/11/2024 | VICTOR CHEN |
| Applicant returned to address corrections | 3/19/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 3/21/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 9/11/2024 | JOSEPH RAFOLS |
| Issued | 9/14/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/16/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 3/6/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 3/6/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 3/11/2024 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/20/2024 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 12/9/2024 | Approved | KEVIN BERBERYAN |
| Deputy Steel/Welding | 1/16/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Conditional Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 2/24/2025 | Partial Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 2/24/2025 | Approved | KEVIN BERBERYAN |
| Deputy Wood Construction | 4/1/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/7/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 4/7/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 4/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/17/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 4/17/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 4/17/2025 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 4/17/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/24/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 5/12/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 5/12/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 5/27/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 8/11/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/21/2025 | Approved | LOUIS ESCOTO |