9535 N BOTHWELL ROAD 91324
Certificate Information: 9535 N BOTHWELL ROAD 91324
- Application / Permit
- 24010-20000-00057
- Plan Check / Job No.
- B24VN00140
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: New 1-story (32' x 26'-6") Single Family Dwelling per SB9 Two-Unit Development Ca Govt. Code 65852.21. All work per Wood Frame Prescriptive Provisions. NFPA 13D Fire Sprinklers Throughout.
- Permit Issued
- Issued on 10/14/2024
- Issuing Office
- Current Status
- Issued on 10/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 1/29/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 1/29/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 6/21/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 10/4/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 10/11/2024 | VAHAN JIVALAGIAN |
| Issued | 10/14/2024 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/7/2024 | NATHAN ROMINE |
| ZA Case | Cleared | 2/7/2024 | NATHAN ROMINE |
| Address approval | Cleared | 2/8/2024 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2024 | BRYAN GODINEZ |
| Sewer availability | Cleared | 2/12/2024 | BRYAN GODINEZ |
| Hydrant and Access approval | Cleared | 3/23/2024 | GILBERT URREA |
| Senate Bill 9 | Cleared | 6/6/2024 | NATHAN ROMINE |
| Low Impact Development (LID) | Cleared | 6/15/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/20/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/18/2024 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 11/22/2024 | Conditional Approval | KRISTEN CAUSEY |
| Green Building Rough | 12/6/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2024 | Partial Approval | DAVID SCANTLIN |
| Interior/Exterior Lathing | 1/7/2025 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 1/30/2025 | Approved | DAVID SCANTLIN |
| Green Building Rough | 1/30/2025 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 1/30/2025 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 1/30/2025 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 2/6/2025 | Approved | DAVID SCANTLIN |
| Final | 4/3/2025 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 4/3/2025 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 5/14/2025 | Not Ready for Inspection | KRISTEN CAUSEY |