5619 N KATHERINE AVE 91401
Certificate Information: 5619 N KATHERINE AVE 91401
- Application / Permit
- 24010-20000-00054
- Plan Check / Job No.
- B24VN00136
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story (43' x 31'-6" Irr Shape) Single Family Dwelling w/Garage and Trellis Patio Cover. NFPA 13D Fire Sprinklers Throughout
- Permit Issued
- Issued on 12/17/2025
- Issuing Office
- Current Status
- Issued on 12/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 1/27/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 1/29/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 1/30/2024 | APPLICANT |
| Plan Check Approved | 12/15/2025 | VAHAN JIVALAGIAN |
| Issued | 12/17/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/1/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 2/7/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 2/7/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 3/2/2024 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/28/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 1/30/2026 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 2/4/2026 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/4/2026 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2026 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2026 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/7/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/7/2026 | Approved | VINCENT HANLEY |
| Underground Mechanical | 4/7/2026 | Partial Inspection | VINCENT HANLEY |
| HVAC-Rough | 4/14/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/20/2026 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 4/20/2026 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 4/20/2026 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2026 | Approved | VINCENT HANLEY |
| Shower Pan | 4/21/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/28/2026 | Approved | VINCENT HANLEY |
| Insulation | 4/28/2026 | Not Ready for Inspection | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/28/2026 | Partial Approval | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 4/28/2026 | Approved | VINCENT HANLEY |
| Insulation | 5/4/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/4/2026 | Not Ready for Inspection | VINCENT HANLEY |
| Drywall Nailing | 5/14/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/14/2026 | Approved | VINCENT HANLEY |