18932 1/2 W ARMINTA ST 91335

Certificate Information: 18932 1/2 W ARMINTA ST 91335

Application / Permit
24010-20000-00051
Plan Check / Job No.
B24VN00131
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN NEW DETACHED SFD per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/27/2024
Issuing Office
Current Status
CofO Issued on 2/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 RAPHAEL ROSAS
Corrections Issued 1/30/2024 RAPHAEL ROSAS
Quality Review Completed 2/9/2024 STEVEN KIM
Applicant returned to address corrections 3/26/2024 RAPHAEL ROSAS
Plan Check Approved 3/26/2024 RAPHAEL ROSAS
Issued 3/27/2024 APPLICANT
CofO in Progress 1/7/2026 ARUTYUN MADATYAN
Permit Finaled 2/19/2026 JOHN JANSON
CofO Issued 2/19/2026 JOHN JANSON
Permit Finaled 2/19/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/30/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/31/2024 EDGAR ALCARAZ
ZA Case Cleared 2/8/2024 ASHLEY RODARTE
ZA Case Cleared 2/8/2024 ASHLEY RODARTE
Senate Bill 9 Cleared 2/12/2024 ASHLEY RODARTE
Hydrant and Access approval Cleared 3/2/2024 RUEL COLE
Low Impact Development (LID) Cleared 3/4/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 3/5/2024 LEE GUILBEAUX
Sewer availability Cleared 3/5/2024 LEE GUILBEAUX
Tract Map conditions Cleared 3/18/2024 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/6/2024 Approved JEFFREY BULL
Footing/Foundation/Slab 9/6/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 10/22/2024 Not Ready for Inspection JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Partial Approval JEFFREY BULL
Green Building Rough 10/22/2024 Not Ready for Inspection JEFFREY BULL
Verify Sprinkler Sign Off 10/22/2024 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 11/21/2024 Conditional Approval ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 11/21/2024 Approved ARUTYUN MADATYAN
Insulation 11/25/2024 Approved ARUTYUN MADATYAN
Drywall Nailing 12/6/2024 Approved ARUTYUN MADATYAN
Green Building Rough 12/6/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 12/6/2024 Partial Approval ARUTYUN MADATYAN
Sewer 12/6/2024 Approved ARUTYUN MADATYAN
Shower Pan 12/26/2024 Approved KRISTEN CAUSEY
Service/Power Release 4/1/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/7/2025 Approved ARUTYUN MADATYAN
Final 5/7/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 5/7/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 5/7/2025 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 5/7/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 1/6/2026 Approved ARUTYUN MADATYAN
Final 1/6/2026 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 1/6/2026 Approved ARUTYUN MADATYAN
HVAC-Final 1/6/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 1/6/2026 Approved ARUTYUN MADATYAN