11945 N SPROULE AVE 91340

Certificate Information: 11945 N SPROULE AVE 91340

Application / Permit
24010-20000-00050
Plan Check / Job No.
B24VN00130
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 52'-0" x 20'-9" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/1/2024
Issuing Office
Current Status
CofO Issued on 4/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2024 APPLICANT
Assigned to Plan Check Engineer 1/10/2024 JEROME MAGAT PALMA
Corrections Issued 1/10/2024 JEROME MAGAT PALMA
Building Plans Picked Up 1/12/2024 APPLICANT
Plan Check Approved 2/26/2024 ARAMIK SHAHMIRZAIAN
Issued 3/1/2024 APPLICANT
CofO in Progress 4/11/2025 MICHEL ABAJAN
Permit Finaled 4/22/2025 RUBEN SALAS
CofO Issued 4/22/2025 RUBEN SALAS
Permit Finaled 4/22/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/16/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/17/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/17/2024 EDGAR ALCARAZ
Construction near power lines Cleared 1/18/2024 OSCAR CASTRO
Low Impact Development (LID) Cleared 2/16/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 2/16/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/22/2024 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 7/5/2024 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 7/17/2024 Approved MICHEL ABAJAN
Footing/Foundation/Slab 7/17/2024 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 9/30/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 11/14/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 11/14/2024 Approved MICHEL ABAJAN
HVAC-Rough 12/2/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/2/2024 Approved MICHEL ABAJAN
Shower Pan 12/2/2024 Approved MICHEL ABAJAN
Wood Frame 12/2/2024 Approved MICHEL ABAJAN
Insulation 12/6/2024 Approved MICHEL ABAJAN
Drywall Nailing 12/13/2024 Approved MICHEL ABAJAN
Green Building Rough 12/13/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/10/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/10/2025 Approved MICHEL ABAJAN
Final 4/10/2025 OK to Issue CofO MICHEL ABAJAN
Green Building Final 4/10/2025 Approved MICHEL ABAJAN
HVAC-Final 4/10/2025 Approved MICHEL ABAJAN
PLUMBING-Final 4/10/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/10/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 4/10/2025 Approved MICHEL ABAJAN
Smoke Detectors 4/10/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 4/10/2025 Approved MICHEL ABAJAN