4252-4254 S RAYMOND AVE 90037

Certificate Information: 4252-4254 S RAYMOND AVE 90037

Application / Permit
24010-20000-00040
Plan Check / Job No.
B24VN00085
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
*EPLAN* NEW 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE. NFPA 13D
Permit Issued
Issued on 4/30/2024
Issuing Office
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2024 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 VIVIAN LAO
Corrections Issued 1/14/2024 VIVIAN LAO
Quality Review Completed 1/18/2024 GARO TELMI
Applicant returned to address corrections 4/10/2024 VIVIAN LAO
Plan Check Approved 4/19/2024 VIVIAN LAO
Issued 4/30/2024 APPLICANT
CofO in Progress 11/8/2024 ALEJANDRO DE ARTOLA
Permit Finaled 11/13/2024 DEROLD HAUFF
CofO Issued 11/13/2024 DEROLD HAUFF
Permit Finaled 11/13/2024 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 1/25/2024 SAMUEL LINN
Address approval Cleared 2/1/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 2/1/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/5/2024 WALLIE JONG
Sewer availability Cleared 2/6/2024 WALLIE JONG
Hydrant and Access approval Cleared 3/1/2024 MATTHEW CRAIG
SB8 RUD Cleared 3/29/2024 KEVIN SCHULTZ

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval SABAS ALONSO
Underground Mechanical 5/31/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Corrections Issued ANTHONY EGSON
Insulation 6/3/2024 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval SABAS ALONSO
Sewer 6/4/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Approved SABAS ALONSO
HVAC-Rough 7/26/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 7/26/2024 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 7/29/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 7/29/2024 Approved SABAS ALONSO
Green Building Rough 7/29/2024 Approved SABAS ALONSO
PLUMBING-Rough 7/29/2024 Approved SABAS ALONSO
Verify Sprinkler Sign Off 7/29/2024 Approved SABAS ALONSO
Insulation 7/31/2024 Approved ALEX COLIN
Drywall Nailing 8/12/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 8/12/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 9/27/2024 Partial Approval SABAS ALONSO
ELECTRICAL-Final 10/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 10/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 10/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 10/7/2024 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 10/7/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/9/2024 Approved ALEJANDRO DE ARTOLA
Final 10/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 10/9/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 10/9/2024 Order to Comply Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/9/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 10/9/2024 Approved ALEJANDRO DE ARTOLA
Final 11/7/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
Service/Power Release 11/7/2024 Approved ALEJANDRO DE ARTOLA