15849 W MARLIN PL 91406
Certificate Information: 15849 W MARLIN PL 91406
- Application / Permit
- 24010-20000-00035
- Plan Check / Job No.
- B24VN00074
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20'-3" X 39'-9" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 1/17/2024
- Issuing Office
- Current Status
- CofO Issued on 6/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 1/8/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 1/10/2024 | APPLICANT |
| Issued | 1/17/2024 | APPLICANT |
| CofO in Progress | 5/28/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 6/6/2025 | RUBEN SALAS |
| CofO Issued | 6/6/2025 | RUBEN SALAS |
| Permit Finaled | 6/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/12/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 1/17/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 1/17/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 2/16/2024 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 4/23/2024 | Approved | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 4/23/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/1/2024 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 5/1/2024 | Approved | RAUL OLAGI |
| Insulation | 5/6/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 5/6/2024 | Partial Approval | SALVADOR MARTINEZ |
| Shower Pan | 5/6/2024 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 5/21/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 5/21/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 5/21/2024 | Approved | MATTHEW NELSON |
| Sewer | 7/16/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 7/16/2024 | Partial Approval | RAUL OLAGI |
| Underground Mechanical | 7/23/2024 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 7/26/2024 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 7/30/2024 | Approved | RAUL OLAGI |
| Final | 11/19/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 11/19/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 11/19/2024 | SGSOV No Gas | GAREN HAYRAPETYAN |
| Service/Power Release | 11/19/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 11/19/2024 | Approved | GAREN HAYRAPETYAN |
| Final | 1/9/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 1/9/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 1/9/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 1/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Service/Power Release | 1/14/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 5/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Service/Power Release | 5/1/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 5/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Service/Power Release | 5/15/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 5/19/2025 | Approved | JENNIFER RABUCHIN |
| Final | 5/19/2025 | Partial Approval | JENNIFER RABUCHIN |
| Service/Power Release | 5/19/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/20/2025 | Approved | JENNIFER RABUCHIN |
| Final | 5/20/2025 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Final | 5/20/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/20/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/20/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 5/20/2025 | Approved | JENNIFER RABUCHIN |
| Final | 5/28/2025 | OK to Issue CofO | JENNIFER RABUCHIN |