313 N BOWLING GREEN WAY 90049
Certificate Information: 313 N BOWLING GREEN WAY 90049
- Application / Permit
- 24010-20000-00034
- Plan Check / Job No.
- B24VN00071
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story Accessory Dwelling Unit (41' x 17' Irregular Shape) per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33(c)-(d), (g). NFPA 13D Fire Sprinklers Throughout.
- Permit Issued
- Issued on 4/7/2025
- Issuing Office
- Valley
- Current Status
- Issued on 4/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 1/13/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 1/17/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 1/18/2024 | APPLICANT |
| Applicant returned to address corrections | 2/12/2025 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 3/28/2025 | VAHAN JIVALAGIAN |
| Plan Check Approved | 4/2/2025 | ALFRED RAMIREZ |
| Issued | 4/7/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/30/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2024 | DARIN LAM |
| Sewer availability | Cleared | 2/6/2024 | DARIN LAM |
| Construction near power lines | Cleared | 2/23/2024 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 4/5/2024 | TOMMY YIN |
| Hydrant and Access approval | Cleared | 4/11/2024 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 4/22/2024 | DARIN LAM |
| GPI Written Notices | Cleared | 3/28/2025 | VAHAN JIVALAGIAN |
| Grading Pre-Inspection | Cleared | 3/28/2025 | VAHAN JIVALAGIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/28/2025 | Partial Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 6/12/2025 | Conditional Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/15/2025 | Partial Approval | JESUS PINEDA |
| Deputy Reinf. Concrete | 7/17/2025 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 7/17/2025 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 9/30/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 9/30/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/30/2025 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Approved | CARLOS MATAMOROS |
| Shower Pan | 10/15/2025 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 11/3/2025 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 11/3/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 11/3/2025 | Approved | CARLOS MATAMOROS |
| Shower Pan | 11/3/2025 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 11/3/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 11/4/2025 | No Access for Inspection | KEVIN SARGSYAN |
| Shower Pan | 11/4/2025 | No Access for Inspection | KEVIN SARGSYAN |
| Insulation | 11/12/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 11/14/2025 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 11/19/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 6/25/2026 | Approved | EVAN COOPER |
| HVAC-Final | 6/25/2026 | Approved | EVAN COOPER |
| PLUMBING-Final | 6/25/2026 | Approved | EVAN COOPER |