348 1/4-1/2 W 68TH ST 90003

Certificate Information: 348 1/4-1/2 W 68TH ST 90003

Application / Permit
24010-20000-00028
Plan Check / Job No.
B24VN00058
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
<ePLAN> NEW 34'11-1/4" X 29'8-1/8" 2-STORY BUILDING CONSISTING OF 2 ADUS (ONE ON EACH FLOOR) PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g) {ALL ELECTRIC BUILDING}
Permit Issued
Issued on 5/14/2024
Issuing Office
Current Status
Issued on 5/14/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/3/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 MARVEL DELACRUZ
Corrections Issued 1/26/2024 MARVEL DELACRUZ
Quality Review Completed 1/29/2024 OMID HEDAYAT
Applicant returned to address corrections 3/29/2024 MARVEL DELACRUZ
Plan Check Approved 5/10/2024 MARVEL DELACRUZ
Issued 5/14/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/30/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/30/2024 JEANIE LAM
Sewer availability Cleared 1/30/2024 JEANIE LAM
Hydrant and Access approval Cleared 3/9/2024 GILBERT URREA
Low Impact Development (LID) Cleared 3/14/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 4/9/2024 JUSTIN BICOL

Contact Information

Contractor Jarh Builders Corporation; Lic. No.: 1074687-B 15740 PARAMOUNT BLVD #E      PARAMOUNT, CA 90723
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/7/2025 Approved JOHN QUINTANILLA
Underground Mechanical 3/7/2025 Approved JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 3/18/2025 Conditional Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Conditional Approval JOHN QUINTANILLA
ELECTRICAL-Rough 8/6/2025 Approved JOHN QUINTANILLA
HVAC-Rough 8/6/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 8/6/2025 Approved JOHN QUINTANILLA
Sewer 8/6/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 10/3/2025 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Conditional Approval MICHAEL LEWIS
Green Building Rough 10/3/2025 Corrections Issued MICHAEL LEWIS
Wood Frame 10/3/2025 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/14/2025 Conditional Approval JOHN QUINTANILLA
Green Building Rough 10/14/2025 Conditional Approval JOHN QUINTANILLA
Insulation 10/14/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 10/14/2025 Not Ready for Inspection JOHN QUINTANILLA
MERV13>=Rough 10/14/2025 Approved JOHN QUINTANILLA
Verify Sprinkler Sign Off 10/14/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 10/17/2025 Approved ANTHONY RAMOS
Drywall Nailing 10/28/2025 Approved BRENDAN MORELLI
Green Building Rough 10/28/2025 Approved BRENDAN MORELLI
ELECTRICAL-Final 5/4/2026 Corrections Issued JOHN QUINTANILLA
HVAC-Final 5/4/2026 Corrections Issued JOHN QUINTANILLA
PLUMBING-Final 5/4/2026 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 5/29/2026 Approved JOHN QUINTANILLA
Final 5/29/2026 Corrections Issued JOHN QUINTANILLA
Footing/Foundation/Slab 5/29/2026 Approved JOHN QUINTANILLA
Green Building Final 5/29/2026 Approved JOHN QUINTANILLA
MERV13>=Final 5/29/2026 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Not Required JOHN QUINTANILLA
Service/Power Release 5/29/2026 Approved JOHN QUINTANILLA
Smoke Detectors 5/29/2026 Approved JOHN QUINTANILLA
Final 6/8/2026 Conditional Approval JOHN QUINTANILLA