348 1/4-1/2 W 68TH ST 90003
Certificate Information: 348 1/4-1/2 W 68TH ST 90003
- Application / Permit
- 24010-20000-00028
- Plan Check / Job No.
- B24VN00058
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- <ePLAN> NEW 34'11-1/4" X 29'8-1/8" 2-STORY BUILDING CONSISTING OF 2 ADUS (ONE ON EACH FLOOR) PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g) {ALL ELECTRIC BUILDING}
- Permit Issued
- Issued on 5/14/2024
- Issuing Office
- Current Status
- Issued on 5/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | MARVEL DELACRUZ |
| Corrections Issued | 1/26/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 1/29/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 3/29/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 5/10/2024 | MARVEL DELACRUZ |
| Issued | 5/14/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/30/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2024 | JEANIE LAM |
| Sewer availability | Cleared | 1/30/2024 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 3/9/2024 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 3/14/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 4/9/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Jarh Builders Corporation; Lic. No.: 1074687-B | 15740 PARAMOUNT BLVD #E PARAMOUNT, CA 90723 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/7/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 3/7/2025 | Approved | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 3/18/2025 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Conditional Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 8/6/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 8/6/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 8/6/2025 | Approved | JOHN QUINTANILLA |
| Sewer | 8/6/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 10/3/2025 | Conditional Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Conditional Approval | MICHAEL LEWIS |
| Green Building Rough | 10/3/2025 | Corrections Issued | MICHAEL LEWIS |
| Wood Frame | 10/3/2025 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/14/2025 | Conditional Approval | JOHN QUINTANILLA |
| Green Building Rough | 10/14/2025 | Conditional Approval | JOHN QUINTANILLA |
| Insulation | 10/14/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 10/14/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| MERV13>=Rough | 10/14/2025 | Approved | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 10/14/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 10/17/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 10/28/2025 | Approved | BRENDAN MORELLI |
| Green Building Rough | 10/28/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/4/2026 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Final | 5/4/2026 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Final | 5/4/2026 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 5/29/2026 | Approved | JOHN QUINTANILLA |
| Final | 5/29/2026 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 5/29/2026 | Approved | JOHN QUINTANILLA |
| Green Building Final | 5/29/2026 | Approved | JOHN QUINTANILLA |
| MERV13>=Final | 5/29/2026 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Not Required | JOHN QUINTANILLA |
| Service/Power Release | 5/29/2026 | Approved | JOHN QUINTANILLA |
| Smoke Detectors | 5/29/2026 | Approved | JOHN QUINTANILLA |
| Final | 6/8/2026 | Conditional Approval | JOHN QUINTANILLA |