16723 W LA MAIDA ST 91436
Certificate Information: 16723 W LA MAIDA ST 91436
- Application / Permit
- 24010-20000-00026
- Plan Check / Job No.
- B24VN00056
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING (3636 SQFT) (43'-6"x73'-0"), W/ATTACHED 2-CAR GARAGE (351 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT. ALL ELECTRIC BUILDING
- Permit Issued
- Issued on 9/30/2025
- Issuing Office
- Valley
- Current Status
- Issued on 9/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | PETER MOSESIAN |
| Corrections Issued | 1/14/2024 | PETER MOSESIAN |
| Quality Review Completed | 1/18/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 1/18/2024 | APPLICANT |
| Plan Check Approved | 4/5/2024 | PETER MOSESIAN |
| Issued | 9/30/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 1/29/2024 | COLIN LOREDO |
| Trees in Parkway | Cleared | 2/29/2024 | ADALBERTO VERA |
| Permit | Cleared | 3/4/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/19/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 3/19/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 3/20/2024 | CARLOS AGUILERA |
| Disturb/Remove Protected Trees | Cleared | 9/17/2025 | RICHARD SANCHEZ |
| Hold | Cleared | 12/9/2025 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/11/2025 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 12/11/2025 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/16/2025 | Corrections Issued | THOMAS FINNILA |
| Deputy Reinf. Concrete | 12/17/2025 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 12/19/2025 | Partial Approval | JOHN HAYES |
| Deputy Steel/Welding | 12/24/2025 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2025 | Partial Approval | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Ready | THOMAS FINNILA |
| Sewer | 12/30/2025 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 1/23/2026 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/29/2026 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2026 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 1/29/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 1/30/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 2/5/2026 | Approved | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2026 | Corrections Issued | THOMAS FINNILA |
| Wood Frame | 2/10/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 2/13/2026 | Corrections Issued | THOMAS FINNILA |
| Insulation | 2/17/2026 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/23/2026 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2026 | Partial Approval | MORRIS JACKSON |
| Wood Frame | 2/23/2026 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Rough | 2/25/2026 | Approved | THOMAS FINNILA |
| HVAC-Rough | 2/25/2026 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 2/25/2026 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/27/2026 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 2/27/2026 | Corrections Issued | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 2/27/2026 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/3/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 3/3/2026 | Approved | THOMAS FINNILA |
| Insulation | 3/3/2026 | Corrections Issued | THOMAS FINNILA |
| Insulation | 3/5/2026 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/11/2026 | Conditional Approval | THOMAS FINNILA |
| Drywall Nailing | 3/11/2026 | Approved | THOMAS FINNILA |
| Insulation | 3/11/2026 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/11/2026 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 5/13/2026 | Partial Approval | THOMAS FINNILA |