4129 S CENTINELA AVE 90066
Certificate Information: 4129 S CENTINELA AVE 90066
- Application / Permit
- 24010-10002-02877
- Plan Check / Job No.
- B25LA27176
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SUPPLEMENTAL TO 24010-10000-02877 FOR EARLY START FOUNDATION ONLY (ED1, 100% AFFORDABLE HOUSING)
- Permit Issued
- Issued on 9/24/2025
- Issuing Office
- Current Status
- Issued on 9/24/2025
Permit Application Status History
| Submitted | 7/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2025 | VU NGUYEN |
| Corrections Issued | 7/1/2025 | VU NGUYEN |
| Applicant returned to address corrections | 8/7/2025 | VU NGUYEN |
| Applicant returned to address corrections | 9/9/2025 | VU NGUYEN |
| Plan Check Approved | 9/19/2025 | VU NGUYEN |
| Issued | 9/24/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/28/2025 | TINA MIRANDA |
| Density Bonus | Cleared | 7/28/2025 | NATHANAEL FORAND |
| Green Code | Cleared | 7/30/2025 | VU NGUYEN |
| Address approval | Cleared | 8/4/2025 | CARLOS AGUILERA |
| Bicycle Parking | Cleared | 8/4/2025 | CARLOS AGUILERA |
| Highway dedication | Cleared | 8/4/2025 | CARLOS AGUILERA |
| Highway dedication | Cleared | 8/4/2025 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 8/4/2025 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 8/4/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/4/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2025 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 8/11/2025 | MARTIN FRAGOSO |
| Trees in Parkway | Cleared | 8/12/2025 | MIGUEL ORNELAS |
| Density Bonus | Cleared | 8/13/2025 | NATHANAEL FORAND |
| Fire Marshal Fire Life Safety | Cleared | 8/20/2025 | FIRE DEPARTMENT |
| Permit | Cleared | 8/20/2025 | CARLOS AGUILERA |
| Frnt yard landscape/Water mgmt | Cleared | 8/21/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/21/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/21/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/21/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/21/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/21/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/21/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/21/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/21/2025 | JAZMIN ROQUE |
| ZA Case | Cleared | 8/21/2025 | JAZMIN ROQUE |
| Hydrant and Access approval | Cleared | 8/25/2025 | LAVEON RIDER |
| DAS Clearance | Cleared | 8/29/2025 | ELIZABETH TOMS |
| Specific Plan | Cleared | 9/4/2025 | RICHARD WOO |
Contact Information
| Architect | , ; Lic. No.: C34124 | , |
| Contractor | Steiner Douglas Construction Inc; Lic. No.: 916002-B | , |
| Engineer | Pukkanasut,, Jirayus; Lic. No.: C73728 | 1424 ROLLING HILLS DR FULLERTON, CA 92835 |
| Engineer | Xia,, Ji; Lic. No.: S7144 | 260 S LOS ROBLES AVE, STE 100 PASADENA, CA 91101 |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/10/2025 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 11/12/2025 | Conditional Approval | GRANT WOODS |
| Reinforced Concrete Frame | 11/26/2025 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 12/1/2025 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 12/11/2025 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 12/11/2025 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 12/15/2025 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 12/15/2025 | Approved | VASIL MIHALEV |
| Footing/Foundation/Slab | 12/15/2025 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 1/5/2026 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2026 | Not Ready for Inspection | DERRICK SPENCER |
| Order to Comply | 1/6/2026 | Not Required | DERRICK SPENCER |
| Deputy Reinf. Concrete | 1/7/2026 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 1/16/2026 | Approved | DERRICK SPENCER |
| Order to Comply | 1/16/2026 | Not Required | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 1/22/2026 | Conditional Approval | PAUL DAVIDSON |
| Pre-Inspection | 1/22/2026 | Approved | ROGELIO REYNA |
| Deputy Reinf. Concrete | 2/12/2026 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/12/2026 | Partial Approval | DERRICK SPENCER |
| Order to Comply | 2/13/2026 | Not Required | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2026 | Partial Approval | DERRICK SPENCER |
| Deputy Wood Construction | 3/31/2026 | Approved | DERRICK SPENCER |