3654 W BOYCE AVE 90039
Certificate Information: 3654 W BOYCE AVE 90039
- Application / Permit
- 24010-10000-05386
- Plan Check / Job No.
- B24LA38209
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. NEW DETACHED ADU PER LAMC 12.22 A.33(c) AND (d). WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 9/4/2025
- Issuing Office
- Current Status
- CofO Issued on 4/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2025 | EDWIN MARTINEZ |
| Corrections Issued | 1/7/2025 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 8/7/2025 | EDWIN MARTINEZ |
| Plan Check Approved | 8/15/2025 | EDWIN MARTINEZ |
| Issued | 9/4/2025 | APPLICANT |
| CofO in Progress | 4/8/2026 | NICHOLAS LOPEZ |
| Permit Finaled | 4/8/2026 | DEROLD HAUFF |
| CofO Issued | 4/8/2026 | DEROLD HAUFF |
| Permit Finaled | 4/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2025 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 2/6/2025 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2025 | CHRISTINA BRACO |
| Sewer availability | Cleared | 2/11/2025 | CHRISTINA BRACO |
| Construction near power lines | Cleared | 8/8/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/8/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Rahban Development; Lic. No.: 1089793-B | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/7/2025 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 10/7/2025 | Partial Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 10/9/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Deputy Drilled-In Anchors | 10/24/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 11/5/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 11/5/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Insulation | 11/5/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 11/5/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 11/10/2025 | Not Ready for Inspection | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 11/13/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 11/13/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 11/13/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 11/13/2025 | Partial Approval | NICHOLAS LOPEZ |
| Verify Sprinkler Sign Off | 11/13/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 11/26/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 12/15/2025 | Approved | GEM DE OCAMPO |
| Shower Pan | 12/15/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 12/31/2025 | Approved | GEM DE OCAMPO |
| ELECTRICAL-Final | 3/17/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 3/17/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 3/17/2026 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 3/17/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 3/17/2026 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 3/17/2026 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/17/2026 | SGSOV No Gas | NICHOLAS LOPEZ |
| Service/Power Release | 3/17/2026 | Not Required | NICHOLAS LOPEZ |
| Smoke Detectors | 3/17/2026 | Approved | NICHOLAS LOPEZ |
| Final | 3/20/2026 | Conditional Approval | NICHOLAS LOPEZ |
| Green Building Final | 3/20/2026 | Approved | NICHOLAS LOPEZ |
| Final | 4/7/2026 | OK to Issue CofO | NICHOLAS LOPEZ |