1408 N CORONADO ST 90026
Certificate Information: 1408 N CORONADO ST 90026
- Application / Permit
- 24010-10000-05384
- Plan Check / Job No.
- B24LA38198
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. NEW DETACHED ADU PER CA GOVT. CODE 65852.2(e)(1)(B) AND APPLICABLE PART OF LAMC 12.22A.33(c)-(d), (g) AND ATTACHED STORAGE (19 S.F.).
- Permit Issued
- Issued on 5/21/2025
- Issuing Office
- Current Status
- CofO Issued on 1/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 1/7/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 4/17/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 4/23/2025 | GIOVANNY CHAVEZ |
| Issued | 5/21/2025 | APPLICANT |
| CofO in Progress | 1/30/2026 | HAMIK HARTOUNIAN |
| Permit Finaled | 1/30/2026 | DEROLD HAUFF |
| CofO Issued | 1/30/2026 | DEROLD HAUFF |
| Permit Finaled | 1/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/15/2025 | ALEXANDER HELFER |
| Address approval | Cleared | 1/17/2025 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 1/17/2025 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 1/17/2025 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 1/17/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 1/24/2025 | CELINA MORENO |
| Sewer availability | Cleared | 1/24/2025 | CELINA MORENO |
| GPI Written Notices | Cleared | 2/26/2025 | GIOVANNY CHAVEZ |
| Construction near power lines | Cleared | 3/1/2025 | TINA MIRANDA |
Contact Information
| Contractor | Smart Eye Construction Corp; Lic. No.: 1077004-B | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/29/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Partial Approval | REGINA MENDEZ |
| Pre-Inspection | 8/1/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 8/11/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 8/13/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 8/13/2025 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/14/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/14/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/14/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/18/2025 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/18/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 8/18/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 8/25/2025 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/4/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 9/4/2025 | Approved | GEM DE OCAMPO |
| Shower Pan | 9/4/2025 | Approved | GEM DE OCAMPO |
| Final | 1/16/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/16/2026 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 1/16/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/16/2026 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Service/Power Release | 1/16/2026 | Not Required | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/16/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 1/26/2026 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 1/26/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 1/30/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |