7521 S EL MANOR AVE 90045
Certificate Information: 7521 S EL MANOR AVE 90045
- Application / Permit
- 24010-10000-05357
- Plan Check / Job No.
- B24LA38017
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-plan. NEW TWO STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 WITH ATTACHED STORAGE
- Permit Issued
- Issued on 5/7/2025
- Issuing Office
- Current Status
- Issued on 5/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | JAD BASMA |
| Corrections Issued | 1/19/2025 | JAD BASMA |
| Quality Review Completed | 1/22/2025 | GARO TELMI |
| Applicant returned to address corrections | 2/27/2025 | JAD BASMA |
| Plan Check Approved | 5/1/2025 | JAD BASMA |
| Issued | 5/7/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/30/2025 | ENRIQUE ACOSTA |
| Address approval | Cleared | 2/3/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2025 | DARIN LAM |
| Sewer availability | Cleared | 2/11/2025 | DARIN LAM |
| Specific Plan | Cleared | 2/12/2025 | FREDDY GARCIA |
| Roof/Waste drainage to street | Cleared | 2/18/2025 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 2/26/2025 | JAD BASMA |
| GPI Written Notices | Cleared | 4/30/2025 | JAD BASMA |
Contact Information
| Architect | Little,, Lisa Kaye; Lic. No.: NA32748 | , |
| Contractor | Pagan Robert M Construction Company; Lic. No.: 509594-B | , |
| Engineer | Chikhale,, Jonathan; Lic. No.: NA78893 | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Masonry Wall/Backfill | 6/25/2025 | Corrections Issued | RUBEN RIVAS |
| Underground Mechanical | 7/18/2025 | Approved | RUBEN RIVAS |
| Footing/Foundation/Slab | 8/4/2025 | Corrections Issued | RUBEN RIVAS |
| METHANE-Barrier | 8/4/2025 | Corrections Issued | RUBEN RIVAS |
| METHANE-Subgrade | 8/4/2025 | Corrections Issued | RUBEN RIVAS |
| Footing/Foundation/Slab | 8/12/2025 | Approved | RUBEN RIVAS |
| Sewer | 8/20/2025 | Corrections Issued | RUBEN RIVAS |
| Underground Mechanical | 8/20/2025 | Partial Approval | RUBEN RIVAS |
| Sewer | 8/22/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 10/24/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 10/24/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Rough | 10/24/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 11/19/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Insulation | 12/9/2025 | Partial Approval | ANTHONY EGSON |
| Shower Pan | 12/9/2025 | Approved | ANTHONY EGSON |
| Insulation | 12/10/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/10/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Shower Pan | 12/10/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 12/31/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/31/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 7/7/2026 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 7/7/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 7/7/2026 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/16/2026 | Approved | MORRIS JACKSON |
| Final | 7/16/2026 | Corrections Issued | MORRIS JACKSON |
| HVAC-Final | 7/16/2026 | Approved | MORRIS JACKSON |
| Service/Power Release | 7/16/2026 | Approved | MORRIS JACKSON |