7521 S EL MANOR AVE 90045

Certificate Information: 7521 S EL MANOR AVE 90045

Application / Permit
24010-10000-05357
Plan Check / Job No.
B24LA38017
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-plan. NEW TWO STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 WITH ATTACHED STORAGE
Permit Issued
Issued on 5/7/2025
Issuing Office
Current Status
Issued on 5/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/7/2025 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 JAD BASMA
Corrections Issued 1/19/2025 JAD BASMA
Quality Review Completed 1/22/2025 GARO TELMI
Applicant returned to address corrections 2/27/2025 JAD BASMA
Plan Check Approved 5/1/2025 JAD BASMA
Issued 5/7/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 1/30/2025 ENRIQUE ACOSTA
Address approval Cleared 2/3/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 2/11/2025 DARIN LAM
Sewer availability Cleared 2/11/2025 DARIN LAM
Specific Plan Cleared 2/12/2025 FREDDY GARCIA
Roof/Waste drainage to street Cleared 2/18/2025 DARIN LAM
Grading Pre-Inspection Cleared 2/26/2025 JAD BASMA
GPI Written Notices Cleared 4/30/2025 JAD BASMA

Contact Information

Architect Little,, Lisa Kaye; Lic. No.: NA32748       ,
Contractor Pagan Robert M Construction Company; Lic. No.: 509594-B       ,
Engineer Chikhale,, Jonathan; Lic. No.: NA78893       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Masonry Wall/Backfill 6/25/2025 Corrections Issued RUBEN RIVAS
Underground Mechanical 7/18/2025 Approved RUBEN RIVAS
Footing/Foundation/Slab 8/4/2025 Corrections Issued RUBEN RIVAS
METHANE-Barrier 8/4/2025 Corrections Issued RUBEN RIVAS
METHANE-Subgrade 8/4/2025 Corrections Issued RUBEN RIVAS
Footing/Foundation/Slab 8/12/2025 Approved RUBEN RIVAS
Sewer 8/20/2025 Corrections Issued RUBEN RIVAS
Underground Mechanical 8/20/2025 Partial Approval RUBEN RIVAS
Sewer 8/22/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 8/28/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 10/24/2025 Approved RUBEN RIVAS
HVAC-Rough 10/24/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 10/24/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 11/19/2025 Approved JESUS RODRIGUEZ
Green Building Rough 11/19/2025 Not Ready for Inspection JESUS RODRIGUEZ
Insulation 12/9/2025 Partial Approval ANTHONY EGSON
Shower Pan 12/9/2025 Approved ANTHONY EGSON
Insulation 12/10/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/10/2025 Not Ready for Inspection ANTHONY EGSON
Shower Pan 12/10/2025 Approved ANTHONY EGSON
Drywall Nailing 12/31/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/31/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 7/7/2026 Corrections Issued EUGENE CASSIDY
HVAC-Final 7/7/2026 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 7/7/2026 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/16/2026 Approved MORRIS JACKSON
Final 7/16/2026 Corrections Issued MORRIS JACKSON
HVAC-Final 7/16/2026 Approved MORRIS JACKSON
Service/Power Release 7/16/2026 Approved MORRIS JACKSON