825 1/2 S SYCAMORE AVE 90036
Certificate Information: 825 1/2 S SYCAMORE AVE 90036
- Application / Permit
- 24010-10000-05335
- Plan Check / Job No.
- B24LA37921
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan* New 2-story detached ADU per LAMC A.33 (c) and (e)
- Permit Issued
- Issued on 6/13/2025
- Issuing Office
- Current Status
- CofO Issued on 2/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | MATTHEW TORRES |
| Corrections Issued | 1/30/2025 | MATTHEW TORRES |
| Quality Review Completed | 2/4/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 5/7/2025 | MATTHEW TORRES |
| Applicant returned to address corrections | 6/3/2025 | MATTHEW TORRES |
| Plan Check Approved | 6/5/2025 | MATTHEW TORRES |
| Issued | 6/13/2025 | APPLICANT |
| CofO in Progress | 2/3/2026 | RONNIE MINDANAO |
| Permit Finaled | 2/6/2026 | DEROLD HAUFF |
| Permit Finaled | 2/6/2026 | DEROLD HAUFF |
| CofO Issued | 2/6/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2025 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 2/11/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2025 | JEANIE LAM |
| Sewer availability | Cleared | 2/13/2025 | JEANIE LAM |
| CPC | Cleared | 2/17/2025 | JAZMIN ROQUE |
Contact Information
| Contractor | Eco Builders & Developers Inc; Lic. No.: 1129244-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/8/2025 | Approved | RONNIE MINDANAO |
| Deputy Methane Barrier | 7/9/2025 | Conditional Approval | RONNIE MINDANAO |
| Deputy Methane Barrier | 7/16/2025 | Conditional Approval | JOSH MEISTER |
| Deputy Methane Barrier | 7/17/2025 | Conditional Approval | RONNIE MINDANAO |
| Deputy Methane Barrier | 7/21/2025 | Conditional Approval | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 7/21/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/21/2025 | Partial Approval | RONNIE MINDANAO |
| METHANE-Barrier | 7/21/2025 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 7/21/2025 | Approved | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 7/23/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2025 | Partial Approval | RONNIE MINDANAO |
| Deputy Wood Construction | 8/21/2025 | Conditional Approval | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 9/5/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 9/5/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Partial Approval | RONNIE MINDANAO |
| Green Building Rough | 9/5/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 9/5/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Final | 9/5/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 9/5/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 9/5/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Underground Mechanical | 9/5/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Verify Sprinkler Sign Off | 9/5/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 9/8/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/8/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 9/9/2025 | Corrections Issued | RONNIE MINDANAO |
| Underground Mechanical | 9/9/2025 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 9/10/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 9/10/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 9/10/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Final | 9/10/2025 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 9/10/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 9/10/2025 | Approved | RONNIE MINDANAO |
| Verify Sprinkler Sign Off | 9/10/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 9/12/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 9/12/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 9/12/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 9/17/2025 | Approved | RONNIE MINDANAO |
| Insulation | 9/29/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 10/6/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 10/6/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 10/6/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 1/12/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 1/12/2026 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 1/12/2026 | Approved | RONNIE MINDANAO |
| Green Building Final | 1/12/2026 | Approved | RONNIE MINDANAO |
| HVAC-Final | 1/12/2026 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 1/12/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 1/12/2026 | SGSOV Approved | RONNIE MINDANAO |
| Service/Power Release | 1/12/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 1/12/2026 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 1/20/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 1/20/2026 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 1/20/2026 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 1/20/2026 | Approved | RONNIE MINDANAO |
| Service/Power Release | 1/20/2026 | Corrections Issued | RONNIE MINDANAO |
| Smoke Detectors | 1/20/2026 | Approved | RONNIE MINDANAO |
| Final | 1/30/2026 | Partial Approval | RONNIE MINDANAO |
| Service/Power Release | 1/30/2026 | Approved | RONNIE MINDANAO |
| Final | 2/3/2026 | OK to Issue CofO | RONNIE MINDANAO |