17851 W STRATHERN ST 91335

Certificate Information: 17851 W STRATHERN ST 91335

Application / Permit
24010-10000-05333
Plan Check / Job No.
B24LA37901
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-PLAN. NEW 2 STORY DETACHED ADU AT REAR OF THE PROPERTY. PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 4/8/2025
Issuing Office
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2024 APPLICANT
Assigned to Plan Check Engineer 1/2/2025 ARSALAN SHABESTARI
Corrections Issued 1/9/2025 ARSALAN SHABESTARI
Quality Review Completed 1/17/2025 YOUNG KIM
Plan Check Approved 4/7/2025 ARSALAN SHABESTARI
Issued 4/8/2025 APPLICANT
CofO in Progress 4/17/2026 ARUTYUN MADATYAN
Permit Finaled 4/30/2026 JOHN JANSON
Permit Finaled 4/30/2026 JOHN JANSON
CofO Issued 4/30/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/14/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/14/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/14/2025 LEE GUILBEAUX
Sewer availability Cleared 1/14/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/14/2025 LEE GUILBEAUX
Construction near power lines Cleared 3/5/2025 GEVORK KARAPETYAN
Construction within easement Cleared 3/5/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/2/2025 Partial Inspection ARUTYUN MADATYAN
PLUMBING-Rough 5/22/2025 Partial Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 5/30/2025 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 5/30/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Partial Approval ARUTYUN MADATYAN
Wood Frame 7/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
Deputy Wood Construction 9/2/2025 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Approved ARUTYUN MADATYAN
Wood Frame 9/4/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 10/7/2025 Corrections Issued ARUTYUN MADATYAN
ELECTRICAL-Rough 10/7/2025 Approved ARUTYUN MADATYAN
Green Building Rough 10/7/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 10/7/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 10/7/2025 Approved ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 10/7/2025 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 10/7/2025 Not Ready for Inspection ARUTYUN MADATYAN
Wood Frame 10/7/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 10/22/2025 Conditional Approval ARUTYUN MADATYAN
Green Building Rough 10/22/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 10/22/2025 Partial Approval ARUTYUN MADATYAN
Insulation 10/31/2025 Not Ready for Inspection ARUTYUN MADATYAN
Sewer 10/31/2025 Not Ready for Inspection ARUTYUN MADATYAN
Insulation 11/5/2025 Approved ARUTYUN MADATYAN
Sewer 11/5/2025 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 11/7/2025 Partial Approval ARUTYUN MADATYAN
Drywall Nailing 11/12/2025 Approved ARUTYUN MADATYAN
Sewer 11/12/2025 Approved ARUTYUN MADATYAN
Shower Pan 11/19/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 11/25/2025 Approved ROBERT GOLD
BUILDING-Rough-Frame 3/13/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 3/13/2026 No Access for Inspection ARUTYUN MADATYAN
Final 3/13/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Final 3/13/2026 Approved ARUTYUN MADATYAN
HVAC-Final 3/13/2026 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 3/13/2026 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 3/13/2026 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 3/13/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 3/18/2026 Approved ARUTYUN MADATYAN
Final 3/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 3/18/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 3/18/2026 Approved ARUTYUN MADATYAN
Service/Power Release 3/18/2026 Not Ready for Inspection ARUTYUN MADATYAN
Final 4/16/2026 OK to Issue CofO ARUTYUN MADATYAN
Service/Power Release 4/16/2026 Approved ARUTYUN MADATYAN