10212 N O'MELVENY AVE 91331

Certificate Information: 10212 N O'MELVENY AVE 91331

Application / Permit
24010-10000-05332
Plan Check / Job No.
B24VN26140
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New detached 2-story ADU per ordinance. 2 OF 2
Permit Issued
Issued on 5/20/2025
Issuing Office
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2024 APPLICANT
Assigned to Plan Check Engineer 12/26/2024 MICHAEL LOPEZ
Corrections Issued 1/8/2025 MICHAEL LOPEZ
Quality Review Completed 1/10/2025 PRANITA SHAH
Applicant returned to address corrections 3/4/2025 KHEDER ALRAZAA
Applicant returned to address corrections 4/2/2025 KHEDER ALRAZAA
Applicant returned to address corrections 4/28/2025 MICHAEL LOPEZ
Applicant returned to address corrections 5/8/2025 MICHAEL LOPEZ
Plan Check Approved 5/14/2025 MICHAEL LOPEZ
Issued 5/20/2025 APPLICANT
CofO in Progress 11/25/2025 MICHEL ABAJAN
CofO Issued 12/18/2025 RUBEN SALAS
Permit Finaled 12/18/2025 RUBEN SALAS

Permit Application Clearance Information

Clean Up Green Up Cleared 1/16/2025 DAVID URITA
Address approval Cleared 1/18/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/18/2025 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/24/2025 RUEL COLE
Eng Process Fee Ord 176,300 Cleared 1/29/2025 CARLOS AGUILERA
Sewer availability Cleared 1/29/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606
Geologist Kaligi,, Adam Azad; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 6/2/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/2/2025 Partial Approval JENNIFER RABUCHIN
Sewer 6/2/2025 Approved JENNIFER RABUCHIN
Underground Mechanical 6/2/2025 Partial Approval JENNIFER RABUCHIN
Deputy Methane Barrier 6/6/2025 Conditional Approval RAUL OLAGI
Deputy Methane Barrier 6/9/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 6/17/2025 Approved MICHEL ABAJAN
METHANE-Barrier 6/17/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 6/17/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 8/6/2025 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/7/2025 Approved MICHEL ABAJAN
Green Building Rough 8/7/2025 Approved MICHEL ABAJAN
METHANE-Rough 8/7/2025 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 8/7/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 8/7/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/11/2025 Approved MICHEL ABAJAN
Insulation 8/13/2025 Approved LOUIS ESCOTO
Drywall Nailing 8/18/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 11/24/2025 Approved MICHEL ABAJAN
Final 11/24/2025 OK to Issue CofO MICHEL ABAJAN
Green Building Final 11/24/2025 Approved MICHEL ABAJAN
HVAC-Final 11/24/2025 Approved MICHEL ABAJAN
PLUMBING-Final 11/24/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/24/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 11/24/2025 Approved MICHEL ABAJAN
Smoke Detectors 11/24/2025 Approved MICHEL ABAJAN