3976 1/2-3/4 S HARVARD BLVD 90062
Certificate Information: 3976 1/2-3/4 S HARVARD BLVD 90062
- Application / Permit
- 24010-10000-05315
- Plan Check / Job No.
- B24LA37805
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (2-UNIT) DETACHED ACCESSORY DWELLING UNIT BUILDING PER STATE LAW
- Permit Issued
- Issued on 2/19/2025
- Issuing Office
- Metro
- Current Status
- Issued on 2/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2025 | NGHI SU |
| Corrections Issued | 1/4/2025 | NGHI SU |
| Building Plans Picked Up | 1/6/2025 | APPLICANT |
| Plan Check Approved | 2/13/2025 | GEORGE ALVAREZ |
| Issued | 2/19/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2025 | DAVID LOPEZ |
| Community Plan Implem. Overlay | Cleared | 1/9/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 1/9/2025 | DAVID LOPEZ |
| Community Plan Implem. Overlay | Cleared | 1/22/2025 | IRA RODRIGUEZ |
| Community Plan Implem. Overlay | Cleared | 1/22/2025 | MANERI ROMAN |
| Community Plan Implem. Overlay | Cleared | 1/22/2025 | RICHARD SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 1/22/2025 | DAVID LOPEZ |
| Community Plan Implem. Overlay | Cleared | 1/30/2025 | RIDWAN HARDY |
| Construction near power lines | Cleared | 1/30/2025 | RIDWAN HARDY |
Contact Information
| Contractor | A-1 Steel Erector; Lic. No.: 931279-B | 9414 ZAMORA AVENUE LOS ANGELES, CA 90002 |
| Engineer | Pinzon,, Eduardo Andres; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/25/2025 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 3/3/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/24/2025 | No Access for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2025 | No Access for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/11/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 4/11/2025 | Approved | SABAS ALONSO |
| Sewer | 4/11/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 4/30/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 4/30/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 4/30/2025 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 4/30/2025 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 5/6/2025 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 5/8/2025 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 5/19/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 5/19/2025 | Approved | SABAS ALONSO |
| Wood Frame | 5/19/2025 | Approved | SABAS ALONSO |
| Insulation | 5/22/2025 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 6/11/2025 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 6/27/2025 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 7/17/2025 | Approved | RONNIE MEDINA |
| BUILDING-Rough-Frame | 11/20/2025 | No Access for Inspection | SABAS ALONSO |
| Green Building Final | 11/20/2025 | No Access for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 11/20/2025 | No Access for Inspection | SABAS ALONSO |
| Final | 11/21/2025 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/26/2025 | Approved | SABAS ALONSO |
| Final | 11/26/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/26/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 11/26/2025 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 11/26/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 1/28/2026 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 1/28/2026 | Approved | SABAS ALONSO |