2237 S PROSPECT AVE 90291

Certificate Information: 2237 S PROSPECT AVE 90291

Application / Permit
24010-10000-05293
Plan Check / Job No.
B24LA34877
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d). FIRE SPRINKLER 13D THROUGH OUT.
Permit Issued
Issued on 6/17/2025
Issuing Office
Current Status
Issued on 6/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/6/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 DANIEL YIP
Corrections Issued 12/26/2024 DANIEL YIP
Quality Review Completed 12/27/2024 GARO TELMI
Applicant returned to address corrections 3/10/2025 DANIEL YIP
Plan Check Approved 4/1/2025 DANIEL YIP
Issued 6/17/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/6/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 2/6/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 2/6/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/6/2025 BIAINA HARITUNIAN
Specific Plan Cleared 2/23/2025 RICHARD WOO
Construction near power lines Cleared 2/27/2025 ENRIQUE ACOSTA
Miscellaneous Cleared 4/1/2025 LIAM ODONOVAN

Contact Information

Architect Hamilton,, Peter W; Lic. No.: NA37714       ,
Contractor M X A Development Inc; Lic. No.: 1023633-B       ,
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/26/2025 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 9/26/2025 Corrections Issued JESUS RODRIGUEZ
Deputy Steel/Welding 9/29/2025 Conditional Approval JESUS RODRIGUEZ
Sewer 10/1/2025 Approved JESUS RODRIGUEZ
Underground Mechanical 10/1/2025 Partial Approval JESUS RODRIGUEZ
Deputy Steel/Welding 10/8/2025 Approved JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/8/2025 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 10/8/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/26/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/29/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/16/2026 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 2/10/2026 Partial Approval RUBEN RIVAS
HVAC-Rough 2/10/2026 Approved RUBEN RIVAS
PLUMBING-Rough 2/10/2026 Approved RUBEN RIVAS
Underground Mechanical 2/10/2026 Approved RUBEN RIVAS
BUILDING-Rough-Frame 4/28/2026 Approved RUBEN RIVAS
Green Building Rough 4/28/2026 Approved RUBEN RIVAS
Verify Sprinkler Sign Off 4/28/2026 Approved RUBEN RIVAS
Interior/Exterior Lathing 4/29/2026 Approved RUBEN RIVAS
Insulation 5/12/2026 Corrections Issued RUBEN RIVAS
Insulation 5/15/2026 Approved RUBEN RIVAS
Drywall Nailing 5/21/2026 Approved RUBEN RIVAS