1034 1/2 N SENTINEL AVE 90063

Certificate Information: 1034 1/2 N SENTINEL AVE 90063

Application / Permit
24010-10000-05246
Plan Check / Job No.
B24LA37318
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY DETACHED ADU PER STATE LAW
Permit Issued
Issued on 3/13/2026
Issuing Office
Metro
Current Status
Issued on 3/13/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/23/2024 APPLICANT
Assigned to Plan Check Engineer 12/24/2024 ADAM HEGAZI
Corrections Issued 12/25/2024 ADAM HEGAZI
Building Plans Picked Up 1/2/2025 APPLICANT
Applicant returned to address corrections 3/24/2025 EDWIN MARTINEZ
Applicant returned to address corrections 1/6/2026 CARLOS MONTES
Plan Check Approved 3/13/2026 NEHEMIAS RAMOS
Issued 3/13/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/23/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 6/15/2025 JESSICA OPINION
Grading Pre-Inspection Cleared 6/16/2025 JONATHAN HOM
Construction near power lines Cleared 7/31/2025 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 9/2/2025 JESSICA OPINION
Sewer availability Cleared 9/2/2025 JESSICA OPINION
GPI Written Notices Cleared 3/13/2026 ADAM HEGAZI

Contact Information

Contractor Owner-Builder       ,
Engineer Mniarji,, Majd Sameer; Lic. No.: C93049 7812 VASSAR AVENUE      CANOGA PARK, CA 91304

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2026 Approved FREDDIE RIVERA
PLUMBING-Rough 5/28/2026 Partial Approval OSVALDO PARAMO
Sewer 5/28/2026 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 6/2/2026 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 6/3/2026 Not Ready for Inspection OSVALDO PARAMO
Deputy Drilled-In Anchors 6/9/2026 Conditional Approval GEM DE OCAMPO
Excavation/Setback/Form/Re-Bar 6/12/2026 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/15/2026 Approved BRENDAN MORELLI
Special/Order Compliance 6/15/2026 Corrections Issued BRENDAN MORELLI
HVAC-Rough 6/30/2026 Approved OSVALDO PARAMO
PLUMBING-Rough 6/30/2026 Approved OSVALDO PARAMO
ELECTRICAL-Rough 7/17/2026 Approved OSVALDO PARAMO