3405 S CABRILLO BLVD 90066

Certificate Information: 3405 S CABRILLO BLVD 90066

Application / Permit
24010-10000-05229
Plan Check / Job No.
B24LA37255
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED, FULLY ELECTRIC ACCESSORY DWELLING UNIT WITH ATTACHED TRELLIS PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN. NFPA-13D FIRE SPRINKLERS TO BE INSTALLED.
Permit Issued
Issued on 5/5/2025
Issuing Office
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2024 APPLICANT
Assigned to Plan Check Engineer 12/27/2024 MADISON ODELL
Corrections Issued 12/28/2024 MADISON ODELL
Applicant returned to address corrections 3/26/2025 MADISON ODELL
Applicant returned to address corrections 4/2/2025 MADISON ODELL
Plan Check Approved 4/9/2025 MADISON O'DELL
Issued 5/5/2025 APPLICANT
Permit Finaled 12/12/2025 RICHARD STEINBACH
Permit Finaled 12/12/2025 RICHARD STEINBACH
CofO Issued 12/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/3/2025 DARIN LAM
Roof/Waste drainage to street Cleared 2/3/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 2/4/2025 DARIN LAM
Sewer availability Cleared 2/4/2025 DARIN LAM
Construction near power lines Cleared 2/13/2025 ENRIQUE ACOSTA
Specific Plan Cleared 3/6/2025 FREDDY GARCIA
Hydrant and Access approval Cleared 4/8/2025 PATRICK PEREZ

Contact Information

Architect Samson,, Charles Andrew H; Lic. No.: C22979 6119 MARY ELLEN AVENUE      VAN NUYS, CA 91401
Contractor Local Construction Remodeling; Lic. No.: 966738-B       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/12/2025 Partial Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 5/20/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 5/20/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 7/3/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 7/3/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 7/3/2025 Approved MICHAEL ALLEN
Green Building Rough 7/3/2025 Approved MICHAEL ALLEN
HVAC-Rough 7/3/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 7/3/2025 Approved MICHAEL ALLEN
Special/Order Compliance 7/3/2025 Corrections Issued MICHAEL ALLEN
Verify Sprinkler Sign Off 7/3/2025 Approved MICHAEL ALLEN
Insulation 7/9/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 7/9/2025 Partial Approval JESUS PINEDA
Shower Pan 7/9/2025 Corrections Issued JESUS PINEDA
Drywall Nailing 7/18/2025 Approved JAYLIN GRAVITTE
Shower Pan 7/18/2025 Approved JAYLIN GRAVITTE
Sewer 8/6/2025 Corrections Issued JAYLIN GRAVITTE
Underground Mechanical 8/6/2025 Partial Approval JAYLIN GRAVITTE
Sewer 9/2/2025 Partial Approval WILBER ROSALES
HVAC-Final 10/28/2025 Approved WILBER ROSALES
PLUMBING-Final 11/4/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 11/5/2025 Approved WILBER ROSALES
Final 11/14/2025 Corrections Issued STEPHANIE SWANSON
Green Building Final 11/14/2025 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Not Required STEPHANIE SWANSON
Service/Power Release 11/14/2025 Approved STEPHANIE SWANSON
Smoke Detectors 11/14/2025 Approved STEPHANIE SWANSON
Service/Power Release 11/17/2025 Partial Inspection WILBER ROSALES
Final 11/19/2025 Not Ready for Inspection WILBER ROSALES
Final 11/26/2025 Conditional Approval WILBER ROSALES