1917 W 41ST PL 90062

Certificate Information: 1917 W 41ST PL 90062

Application / Permit
24010-10000-05207
Plan Check / Job No.
B24LA36990
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. NEW 2-STORY DETACHED ADU (1,200 SF) WITH ATTACHED GARAGE (361 SF).
Permit Issued
Issued on 7/19/2025
Issuing Office
Current Status
Issued on 7/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/19/2024 APPLICANT
Assigned to Plan Check Engineer 12/26/2024 HERNAN ARREOLA
Corrections Issued 12/31/2024 HERNAN ARREOLA
Quality Review Completed 1/2/2025 PETER KIM
Applicant returned to address corrections 2/26/2025 HERNAN ARREOLA
Plan Check Approved 3/12/2025 HERNAN ARREOLA
Issued 7/19/2025 APPLICANT

Permit Application Clearance Information

Hold Cleared 1/9/2025 CARMEN MERAZ
Address approval Cleared 1/10/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 1/10/2025 ADRIAN SANCHEZ
Flood clearance Cleared 2/3/2025 SAMSON WONG
Eng Process Fee Ord 176,300 Cleared 2/4/2025 WALLIE JONG
Sewer availability Cleared 2/4/2025 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/27/2025 Partial Approval SABAS ALONSO
Underground Mechanical 10/27/2025 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 11/3/2025 Corrections Issued SABAS ALONSO
PLUMBING-Final 11/3/2025 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 11/6/2025 Approved SABAS ALONSO
Underground Mechanical 11/6/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 12/4/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 1/15/2026 Corrections Issued SABAS ALONSO
HVAC-Rough 1/15/2026 Corrections Issued SABAS ALONSO
PLUMBING-Rough 1/15/2026 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 1/30/2026 Corrections Issued SABAS ALONSO
HVAC-Rough 1/30/2026 Approved SABAS ALONSO
PLUMBING-Rough 1/30/2026 Approved SABAS ALONSO
ELECTRICAL-Rough 2/4/2026 Approved SABAS ALONSO
Green Building Rough 2/4/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 2/4/2026 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 2/6/2026 Approved SABAS ALONSO
Green Building Rough 2/6/2026 Approved SABAS ALONSO
Insulation 2/18/2026 No Access for Inspection SABAS ALONSO
Insulation 2/20/2026 Approved SABAS ALONSO
Drywall Nailing 3/6/2026 Corrections Issued SABAS ALONSO
Drywall Nailing 3/10/2026 Corrections Issued SABAS ALONSO
Drywall Nailing 3/12/2026 Approved ALEX COLIN
Shower Pan 3/12/2026 Approved ALEX COLIN
Interior/Exterior Lathing 3/25/2026 Approved SABAS ALONSO
Underground Mechanical 5/5/2026 Approved SABAS ALONSO