5507 1/2 S WILTON PL 90062

Certificate Information: 5507 1/2 S WILTON PL 90062

Application / Permit
24010-10000-05206
Plan Check / Job No.
B24LA36989
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY DETACHED ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 4/7/2025
Issuing Office
Current Status
Issued on 4/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/19/2024 APPLICANT
Assigned to Plan Check Engineer 1/2/2025 ARMEN JIVALAGIAN
Corrections Issued 1/7/2025 ARMEN JIVALAGIAN
Quality Review Completed 1/7/2025 PETER KIM
Plan Check Approved 3/28/2025 ARMEN JIVALAGIAN
Issued 4/7/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/4/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/5/2025 WALLIE JONG
Sewer availability Cleared 3/5/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 3/11/2025 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/10/2025 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 4/15/2025 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 4/17/2025 Corrections Issued BARRY HACHE
Excavation/Setback/Form/Re-Bar 7/24/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 7/24/2025 Approved LUIS CASTRO
PLUMBING-Rough 7/24/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Partial Approval BARRY HACHE
BUILDING-Rough-Frame 10/16/2025 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 10/16/2025 Partial Approval RAUL BARAJAS
Green Building Rough 10/16/2025 Approved RAUL BARAJAS
HVAC-Rough 10/16/2025 Approved RAUL BARAJAS
PLUMBING-Rough 10/16/2025 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 10/16/2025 Approved RAUL BARAJAS
BUILDING-Rough-Frame 10/31/2025 Approved ALEX COLIN
Insulation 10/31/2025 Approved ALEX COLIN
Interior/Exterior Lathing 10/31/2025 Partial Approval ALEX COLIN
Rough-Elec/Plmb/HVAC 10/31/2025 Approved ALEX COLIN
Drywall Nailing 2/5/2026 Approved BARRY HACHE
Interior/Exterior Lathing 2/5/2026 Approved BARRY HACHE
Sewer 2/5/2026 Corrections Issued BARRY HACHE
Underground Mechanical 2/5/2026 Approved BARRY HACHE
Sewer 2/10/2026 Approved BARRY HACHE
Service/Power Release 2/26/2026 Corrections Issued BARRY HACHE
Pre-Inspection 3/17/2026 Corrections Issued BARRY HACHE
HVAC-Final 4/16/2026 Not Ready for Inspection JOHN QUINTANILLA