3519 S REDWOOD AVE 90066
Certificate Information: 3519 S REDWOOD AVE 90066
- Application / Permit
- 24010-10000-05192
- Plan Check / Job No.
- B24LA36817
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2). FIRE SPRINKLERS PER NFPA 13D.
- Permit Issued
- Issued on 4/17/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | PRANITA SHAH |
| Corrections Issued | 1/16/2025 | PRANITA SHAH |
| Quality Review Completed | 1/29/2025 | KEN GILL |
| Applicant returned to address corrections | 4/10/2025 | PRANITA SHAH |
| Plan Check Approved | 4/10/2025 | PRANITA SHAH |
| Issued | 4/17/2025 | APPLICANT |
| CofO in Progress | 12/24/2025 | WILBER ROSALES |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/10/2025 | MICHAEL TEMPLE |
| Specific Plan | Cleared | 2/10/2025 | RICHARD WOO |
| Address approval | Cleared | 2/13/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2025 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 2/13/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 2/13/2025 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 4/10/2025 | PRANITA SHAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/23/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 4/23/2025 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 4/23/2025 | Approved | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 5/6/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 7/17/2025 | Conditional Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 7/17/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 7/17/2025 | Partial Approval | MICHAEL ALLEN |
| HVAC-Rough | 7/17/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 7/17/2025 | Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 7/17/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 7/24/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 7/24/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 7/24/2025 | Approved | WILBER ROSALES |
| Insulation | 7/30/2025 | Corrections Issued | WILBER ROSALES |
| Shower Pan | 7/30/2025 | Approved | WILBER ROSALES |
| Insulation | 8/5/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 8/5/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 8/8/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 12/8/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 12/8/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 12/11/2025 | Approved | WILBER ROSALES |
| Final | 12/22/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 12/22/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 12/22/2025 | SGSOV Not Required | WILBER ROSALES |
| Service/Power Release | 12/22/2025 | Approved | WILBER ROSALES |
| Smoke Detectors | 12/22/2025 | Approved | WILBER ROSALES |
| Final | 12/24/2025 | OK to Issue CofO | WILBER ROSALES |