818-818 1/2 E 25TH ST 90011

Certificate Information: 818-818 1/2 E 25TH ST 90011

Application / Permit
24010-10000-05187
Plan Check / Job No.
B24LA36623
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY (2) UNIT ADU PER CA GOVT CODE 65852.2 (E)(1)(C), NO PARKING REQUIRED PER AB2097, AND PER WFPP (REAR)
Permit Issued
Issued on 2/26/2025
Issuing Office
Metro
Current Status
CofO Issued on 9/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 STARR CHEN
Corrections Issued 12/23/2024 STARR CHEN
Quality Review Completed 12/23/2024 EUGENE BARBEAU
Applicant returned to address corrections 2/21/2025 STARR CHEN
Plan Check Approved 2/26/2025 STARR CHEN
Issued 2/26/2025 APPLICANT
CofO in Progress 9/17/2025 ALEJANDRO DE ARTOLA
Permit Finaled 9/21/2025 DEROLD HAUFF
CofO Issued 9/21/2025 DEROLD HAUFF
Permit Finaled 9/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/24/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 12/24/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 12/24/2024 JUSTIN BICOL
Sewer availability Cleared 12/24/2024 JUSTIN BICOL
Hydrant and Access approval Cleared 1/3/2025 JERRY KAO

Contact Information

Contractor So Cal Construction Enterprises Inc; Lic. No.: 832488-B P O BOX 96      SAN GABRIEL, CA 91778

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/27/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 2/27/2025 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 2/28/2025 Approved MICHAEL LEWIS
Footing/Foundation/Slab 2/28/2025 Conditional Approval MICHAEL LEWIS
Sewer 3/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 3/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Partial Approval ALEJANDRO DE ARTOLA
Sewer 3/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Partial Approval ALEJANDRO DE ARTOLA
Sewer 3/18/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 3/21/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/24/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/24/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/26/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 3/26/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/26/2025 Partial Approval ALEJANDRO DE ARTOLA
Insulation 4/3/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 4/8/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 8/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/25/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 8/26/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 8/26/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/5/2025 Approved ALEJANDRO DE ARTOLA
Final 9/5/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/5/2025 Approved ALEJANDRO DE ARTOLA
Green Building Final 9/5/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 9/5/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Smoke Detectors 9/5/2025 Approved ALEJANDRO DE ARTOLA
Final 9/16/2025 OK to Issue CofO ALEJANDRO DE ARTOLA