1423-1423 1/2 E 22ND ST 90011
Certificate Information: 1423-1423 1/2 E 22ND ST 90011
- Application / Permit
- 24010-10000-05184
- Plan Check / Job No.
- B24LA36614
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW TWO STORY TWO UNIT ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2
- Permit Issued
- Issued on 3/4/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | JAD BASMA |
| Corrections Issued | 12/31/2024 | MICHAEL LOPEZ |
| Quality Review Completed | 1/3/2025 | KEN GILL |
| Building Plans Picked Up | 1/15/2025 | APPLICANT |
| Applicant returned to address corrections | 2/20/2025 | JAD BASMA |
| Plan Check Approved | 3/4/2025 | JAD BASMA |
| Issued | 3/4/2025 | APPLICANT |
| CofO in Progress | 9/20/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 9/21/2025 | DEROLD HAUFF |
| CofO Issued | 9/21/2025 | DEROLD HAUFF |
| Permit Finaled | 9/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2025 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2025 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 1/7/2025 | CHRISTINA BRACO |
| Sewer availability | Cleared | 1/7/2025 | CHRISTINA BRACO |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | P O BOX 96 SAN GABRIEL, CA 91778 |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 4/18/2025 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 4/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/1/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 5/1/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 5/1/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 5/1/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 5/1/2025 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 5/1/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 5/2/2025 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 5/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 5/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Final | 9/19/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |