818 1/2 S CURSON AVE 90036
Certificate Information: 818 1/2 S CURSON AVE 90036
- Application / Permit
- 24010-10000-05170
- Plan Check / Job No.
- B24LA36513
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d).
- Permit Issued
- Issued on 8/22/2025
- Issuing Office
- Current Status
- CofO Issued on 7/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | DANIEL YIP |
| Corrections Issued | 1/4/2025 | DANIEL YIP |
| Quality Review Completed | 1/6/2025 | GARO TELMI |
| Plan Check Approved | 5/20/2025 | DANIEL YIP |
| Issued | 8/22/2025 | APPLICANT |
| CofO in Progress | 7/20/2026 | ENRIQUE MIRELES |
| CofO Issued | 7/21/2026 | DEROLD HAUFF |
| Permit Finaled | 7/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction within easement | Cleared | 3/4/2025 | RIDWAN HARDY |
| HPOZ | Cleared | 3/11/2025 | ERIK VAN BREENE |
| Address approval | Cleared | 4/11/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/11/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 5/8/2025 | DAVID LOPEZ |
Contact Information
| Contractor | S J Cons - Tech Co; Lic. No.: 905983-B | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 2450 W MAIN ST ALHAMBRA, CA 91801 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/24/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/24/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 10/24/2025 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 10/24/2025 | Approved | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 11/10/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2025 | Partial Approval | RONNIE MINDANAO |
| Green Building Rough | 11/10/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 11/10/2025 | Approved | RONNIE MINDANAO |
| Verify Sprinkler Sign Off | 11/10/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 12/3/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2025 | Partial Approval | RONNIE MINDANAO |
| Green Building Rough | 12/3/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Verify Sprinkler Sign Off | 12/3/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 1/14/2026 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 1/14/2026 | Corrections Issued | JOSH MEISTER |
| PLUMBING-Rough | 1/23/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Sewer | 1/23/2026 | Partial Approval | RONNIE MINDANAO |
| Underground Mechanical | 1/23/2026 | Corrections Issued | RONNIE MINDANAO |
| Underground Mechanical | 1/27/2026 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 2/3/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 2/3/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 2/3/2026 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 2/3/2026 | Approved | RONNIE MINDANAO |
| Special/Order Compliance | 2/3/2026 | Corrections Issued | RONNIE MINDANAO |
| Verify Sprinkler Sign Off | 2/3/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 2/4/2026 | Approved | RONNIE MINDANAO |
| Special/Order Compliance | 2/4/2026 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 2/5/2026 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 2/5/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 2/5/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 2/5/2026 | Approved | RONNIE MINDANAO |
| Green Building Final | 2/5/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 2/5/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Not Ready | RONNIE MINDANAO |
| Service/Power Release | 2/5/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 2/5/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Insulation | 2/9/2026 | Corrections Issued | ALEX COLIN |
| Drywall Nailing | 2/13/2026 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 2/13/2026 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/5/2026 | Partial Approval | JEFFREY MEAD |
| Interior/Exterior Lathing | 3/17/2026 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 5/11/2026 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 6/4/2026 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 6/4/2026 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 6/8/2026 | Approved | RONNIE MINDANAO |
| HVAC-Final | 6/8/2026 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 6/9/2026 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/29/2026 | Approved | RONNIE MINDANAO |
| Final | 6/29/2026 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 6/29/2026 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 6/29/2026 | SGSOV Not Required | RONNIE MINDANAO |
| Service/Power Release | 6/29/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 6/29/2026 | Approved | RONNIE MINDANAO |
| Verify Sprinkler Sign Off | 6/29/2026 | Approved | RONNIE MINDANAO |
| Final | 7/1/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Service/Power Release | 7/1/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 7/6/2026 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 7/6/2026 | Approved | ENRIQUE MIRELES |