2141-2143 S BENECIA AVE 90025
Certificate Information: 2141-2143 S BENECIA AVE 90025
- Application / Permit
- 24010-10000-05152
- Plan Check / Job No.
- B24LA36428
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. NEW 2 STORY SINGLE FAMILY DWELLING WITH GARAGE, BASEMENT (WITH LIGHTWELL) AND ATTACHED ADU. ***BUILDING TO BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THROUGHOUT***.
- Permit Issued
- Issued on 11/13/2025
- Issuing Office
- Current Status
- Issued on 11/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | CRYSTEL MAALOUF |
| Corrections Issued | 1/13/2025 | CRYSTEL MAALOUF |
| Quality Review Completed | 1/24/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/2/2025 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 4/9/2025 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 4/11/2025 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 5/1/2025 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 7/16/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 11/12/2025 | CRYSTEL MAALOUF |
| Issued | 11/13/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/15/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2025 | DARIN LAM |
| Sewer availability | Cleared | 1/17/2025 | DARIN LAM |
| Specific Plan | Cleared | 2/7/2025 | RICHARD WOO |
| Trees in Parkway | Cleared | 2/20/2025 | MIGUEL ORNELAS |
| Low Impact Development (LID) | Cleared | 2/21/2025 | LUIS LUVANO |
| Permit | Cleared | 2/22/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 2/24/2025 | DARIN LAM |
| Hydrant and Access approval | Cleared | 3/12/2025 | KURT CORRAL |
| GPI Written Notices | Cleared | 10/23/2025 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 10/23/2025 | AL GAMBLE |
| Excavation more than 5-ft deep | Cleared | 11/12/2025 | CALOSHA APPROVED |
Contact Information
| Architect | Borukhim,, Behdad; Lic. No.: C33202 | 6380 WILSHIRE BLVD #1709 LOS ANGELES, CA 90048 |
| Architect | Borukhim,, Behdad; Lic. No.: NA33202 | , |
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Allen Chun-Ying; Lic. No.: C69385 | 2 MILLSTONE IRVINE, CA 92606 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/21/2026 | Approved | CARLOS MATAMOROS |
| METHANE-Subgrade | 2/12/2026 | Approved | DANIEL VERA |
| PLUMBING-Rough | 2/13/2026 | Partial Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 2/13/2026 | Corrections Issued | CARLOS MATAMOROS |
| METHANE-Final | 3/4/2026 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 3/11/2026 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/11/2026 | Partial Approval | CARLOS MATAMOROS |
| METHANE-Barrier | 3/11/2026 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 3/12/2026 | Conditional Approval | RYAN SALAZAR |
| Deputy Reinf. Concrete | 3/18/2026 | Conditional Approval | RYAN SALAZAR |
| Deputy Shotcrete | 4/3/2026 | Conditional Approval | RYAN SALAZAR |
| Reinforced Concrete Frame | 4/3/2026 | Partial Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 4/6/2026 | Conditional Approval | RYAN SALAZAR |
| Deputy Reinf. Concrete | 5/7/2026 | Conditional Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 5/7/2026 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Reinf. Concrete | 5/12/2026 | Conditional Approval | ANDREW NAVE |
| PLUMBING-Rough | 6/18/2026 | Partial Approval | RYAN SALAZAR |
| Sewer | 6/18/2026 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 6/29/2026 | Conditional Approval | DAVID SCANTLIN |
| Deputy Reinf. Concrete | 6/29/2026 | Conditional Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 6/29/2026 | Corrections Issued | DAVID SCANTLIN |