1048 1/2 W 84TH PL 90044

Certificate Information: 1048 1/2 W 84TH PL 90044

Application / Permit
24010-10000-05150
Plan Check / Job No.
B24LA35202
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN PROPOSED SINGLE FAMILY DWELLING WITH A TTACHED 4-CAR GARAGE. NFPA 13D SOLAR INSTALLATION REQUIRED TO MEET KW PER TITLE 24 PRIOR TO COFO.
Permit Issued
Issued on 6/10/2025
Issuing Office
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 MICHAEL LOPEZ
Corrections Issued 12/27/2024 MICHAEL LOPEZ
Quality Review Completed 12/27/2024 PRANITA SHAH
Plan Check Approved 4/3/2025 VIVIAN LAO
Issued 6/10/2025 APPLICANT
CofO in Progress 1/27/2026 JOHN QUINTANILLA
Permit Finaled 1/27/2026 DEROLD HAUFF
CofO Issued 1/27/2026 DEROLD HAUFF
Permit Finaled 1/27/2026 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/22/2025 RUEL COLE
Low Impact Development (LID) Cleared 1/22/2025 ERNEST TSE
Address approval Cleared 2/1/2025 PAMELA TENEZA
Roof/Waste drainage to street Cleared 2/3/2025 TREVOR QUAN
Sewer availability Cleared 2/4/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/8/2025 PAMELA TENEZA
Construction near power lines Cleared 2/25/2025 RIDWAN HARDY
Construction within easement Cleared 2/25/2025 RIDWAN HARDY

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/4/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Partial Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 9/23/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 10/2/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 10/15/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Rough 10/15/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 10/16/2025 Partial Approval JOHN QUINTANILLA
Green Building Rough 10/16/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 10/16/2025 Approved JOHN QUINTANILLA
Verify Sprinkler Sign Off 10/16/2025 Approved JOHN QUINTANILLA
Special/Order Compliance 10/20/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 10/22/2025 Approved ANTHONY RAMOS
Insulation 10/22/2025 Approved ANTHONY RAMOS
Drywall Nailing 10/29/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 10/29/2025 Approved ANTHONY RAMOS
Sewer 11/19/2025 Approved JOHN QUINTANILLA
Underground Mechanical 11/19/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 1/8/2026 Approved JOHN QUINTANILLA
HVAC-Final 1/8/2026 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 1/9/2026 Approved JOHN QUINTANILLA
Final 1/9/2026 Conditional Approval JOHN QUINTANILLA
Green Building Final 1/9/2026 Approved JOHN QUINTANILLA
PLUMBING-Final 1/9/2026 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 1/9/2026 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 1/9/2026 Approved JOHN QUINTANILLA
Smoke Detectors 1/9/2026 Approved JOHN QUINTANILLA
Final 1/13/2026 Conditional Approval JOHN QUINTANILLA
HVAC-Final 1/13/2026 Approved JOHN QUINTANILLA
Final 1/22/2026 OK to Issue CofO JOHN QUINTANILLA
Service/Power Release 1/22/2026 Partial Inspection JOHN QUINTANILLA