Permit Issued
Issued on 3/4/2025
Issuing Office
Metro
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2024 APPLICANT
Assigned to Plan Check Engineer 12/26/2024 SINA KHOSRAVI
Corrections Issued 1/2/2025 SINA KHOSRAVI
Quality Review Completed 1/3/2025 KEN GILL
Building Plans Picked Up 1/6/2025 APPLICANT
Plan Check Approved 2/27/2025 SINA KHOSRAVI
Issued 3/4/2025 APPLICANT
CofO in Progress 10/1/2025 EVAN COOPER
Permit Finaled 10/7/2025 RICHARD STEINBACH
CofO Issued 10/7/2025 RICHARD STEINBACH
Permit Finaled 10/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/14/2025 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 1/24/2025 JESSICA OPINION
Sewer availability Cleared 1/24/2025 JESSICA OPINION
Roof/Waste drainage to street Cleared 1/29/2025 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/11/2025 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 4/17/2025 Approved EVAN COOPER
Footing/Foundation/Slab 4/17/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 5/27/2025 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Corrections Issued BOBBY KEY
HVAC-Rough 5/27/2025 Corrections Issued BOBBY KEY
PLUMBING-Rough 5/27/2025 Approved BOBBY KEY
HVAC-Rough 6/13/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 6/20/2025 Conditional Approval EVAN COOPER
Insulation 6/27/2025 Approved EVAN COOPER
Interior/Exterior Lathing 6/27/2025 Partial Approval EVAN COOPER
Drywall Nailing 7/11/2025 Approved EVAN COOPER
Green Building Rough 7/11/2025 Approved EVAN COOPER
Shower Pan 7/29/2025 Approved EVAN COOPER
Interior/Exterior Lathing 8/4/2025 No Access for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 8/6/2025 Approved EVAN COOPER
PLUMBING-Final 9/3/2025 Approved EVAN COOPER
ELECTRICAL-Final 9/8/2025 Approved EVAN COOPER
Service/Power Release 9/8/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 9/15/2025 Approved EVAN COOPER
Final 9/15/2025 Corrections Issued EVAN COOPER
Green Building Final 9/15/2025 Approved EVAN COOPER
HVAC-Final 9/15/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 9/15/2025 Approved EVAN COOPER
Verify Sprinkler Sign Off 9/15/2025 Approved EVAN COOPER
Final 10/1/2025 OK to Issue CofO EVAN COOPER
Service/Power Release 10/1/2025 Approved EVAN COOPER