10020 S RUTHELEN ST 90047
Certificate Information: 10020 S RUTHELEN ST 90047
- Application / Permit
- 24010-10000-05075
- Plan Check / Job No.
- B24LA35569
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New 1-story detached ADU per at rear of the lot per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 2/24/2025
- Issuing Office
- Current Status
- CofO Issued on 8/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2024 | JOHN MESIAS |
| Corrections Issued | 12/18/2024 | JOHN MESIAS |
| Applicant returned to address corrections | 1/28/2025 | JOHN MESIAS |
| Plan Check Approved | 2/23/2025 | REZA HAGHIGHAT |
| Issued | 2/24/2025 | APPLICANT |
| CofO in Progress | 8/19/2025 | WAYNE REGESTER |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
| CofO Issued | 8/24/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2025 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2025 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 1/10/2025 | CHRISTINA BRACO |
| Sewer availability | Cleared | 1/10/2025 | CHRISTINA BRACO |
Contact Information
| Contractor | Kinslow K W Construction Inc; Lic. No.: 799861-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/27/2025 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 2/27/2025 | Approved | MICHAEL LEWIS |
| METHANE-Rough | 3/3/2025 | Approved | BARRY HACHE |
| Footing/Foundation/Slab | 3/7/2025 | Approved | JOSE MACIAS |
| METHANE-Barrier | 3/7/2025 | Approved | JOSE MACIAS |
| METHANE-Subgrade | 3/7/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/26/2025 | Not Ready for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 3/26/2025 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 4/4/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 4/4/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 4/4/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 4/4/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 4/4/2025 | Approved | WAYNE REGESTER |
| Verify Sprinkler Sign Off | 4/4/2025 | Approved | WAYNE REGESTER |
| Insulation | 4/14/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 4/22/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 4/22/2025 | Approved | ANTHONY RAMOS |
| Final | 6/3/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 6/3/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Not Required | JOSE MACIAS |
| Service/Power Release | 6/3/2025 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 6/3/2025 | Approved | JOSE MACIAS |
| Final | 8/4/2025 | Corrections Issued | WAYNE REGESTER |
| Service/Power Release | 8/4/2025 | Approved | WAYNE REGESTER |
| Final | 8/18/2025 | OK to Issue CofO | WAYNE REGESTER |