4188-4190 S DENKER AVE 90062
Certificate Information: 4188-4190 S DENKER AVE 90062
- Application / Permit
- 24010-10000-05069
- Plan Check / Job No.
- B24LA35505
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: NEW 3-STORY DUPLEX PER ENGINEER DESIGN UNIT 1: 4339.5 SQFT UNIT 2: 4276.5SQFT ***13D SPRINKLER REQUIRED***
- Permit Issued
- Issued on 5/14/2025
- Issuing Office
- Current Status
- Issued on 5/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | KHUONG TRUONG |
| Corrections Issued | 3/6/2025 | KHUONG TRUONG |
| Quality Review Completed | 3/7/2025 | GARO TELMI |
| Plan Check Approved | 4/8/2025 | KHUONG TRUONG |
| Issued | 5/14/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/12/2025 | JOHN CONNEALLY |
| Address approval | Cleared | 3/15/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/15/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/15/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/18/2025 | LEE GUILBEAUX |
| SB8 RUD | Cleared | 3/26/2025 | NATHANAEL FORAND |
| Zoning Plan Check | Cleared | 3/26/2025 | KHUONG TRUONG |
| Low Impact Development (LID) | Cleared | 3/27/2025 | SARAH YOUSSEF |
Contact Information
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/5/2025 | Partial Inspection | SABAS ALONSO |
| Sewer | 8/5/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 8/5/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 8/22/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 8/25/2025 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2025 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Wood Construction | 1/21/2026 | Conditional Approval | SABAS ALONSO |
| PLUMBING-Rough | 1/28/2026 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/24/2026 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 3/24/2026 | Approved | SABAS ALONSO |
| Green Building Rough | 3/24/2026 | Approved | SABAS ALONSO |
| HVAC-Rough | 3/24/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 3/24/2026 | Partial Approval | SABAS ALONSO |
| Verify Sprinkler Sign Off | 3/24/2026 | Approved | SABAS ALONSO |
| Insulation | 3/31/2026 | Not Ready for Inspection | ALEX COLIN |
| Insulation | 4/2/2026 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/15/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/23/2026 | Approved | SABAS ALONSO |
| Shower Pan | 6/23/2026 | Approved | SABAS ALONSO |