14240 W HORTENSE ST 91423

Certificate Information: 14240 W HORTENSE ST 91423

Application / Permit
24010-10000-05054
Plan Check / Job No.
B24LA35290
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE. 2 OF 2
Permit Issued
Issued on 2/14/2025
Issuing Office
Metro
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 JOE VO
Corrections Issued 12/19/2024 MICHAEL LOPEZ
Quality Review Completed 12/23/2024 KEN GILL
Building Plans Picked Up 12/26/2024 APPLICANT
Plan Check Approved 2/13/2025 JOE VO
Issued 2/14/2025 APPLICANT
CofO in Progress 1/22/2026 MISAEL ESPARZA
Permit Finaled 2/12/2026 RUBEN SALAS
CofO Issued 2/12/2026 RUBEN SALAS
Permit Finaled 2/12/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/30/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/30/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/30/2024 CARLOS AGUILERA
Sewer availability Cleared 12/30/2024 CARLOS AGUILERA
ZI Cleared 1/22/2025 BRENNEN OBETO

Contact Information

Contractor K & K Modern Construction; Lic. No.: 1126272-B 12838 KLING ST      STUDIO CITY, CA 91614
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/19/2025 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/21/2025 Partial Approval MISAEL ESPARZA
Pre-Inspection 3/21/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/25/2025 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/28/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/29/2025 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval JACK KARGODORIAN
Green Building Rough 5/29/2025 Approved JACK KARGODORIAN
HVAC-Rough 5/29/2025 Approved JACK KARGODORIAN
MERV13>=Rough 5/29/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 5/29/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 5/29/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 6/6/2025 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 6/18/2025 Approved MISAEL ESPARZA
Insulation 6/30/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/30/2025 Partial Approval VINCENT HANLEY
Drywall Nailing 7/7/2025 Approved LOUIS ESCOTO
Sewer 8/20/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 1/5/2026 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 1/9/2026 Approved MISAEL ESPARZA
HVAC-Final 1/9/2026 Approved MISAEL ESPARZA
PLUMBING-Final 1/9/2026 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 1/14/2026 Approved MISAEL ESPARZA
PLUMBING-Final 1/14/2026 Approved MISAEL ESPARZA
Final 1/20/2026 OK to Issue CofO MISAEL ESPARZA
Footing/Foundation/Slab 1/20/2026 Approved MISAEL ESPARZA
Green Building Final 1/20/2026 Approved MISAEL ESPARZA
MERV13>=Final 1/20/2026 Approved MISAEL ESPARZA
Service/Power Release 1/20/2026 Approved MISAEL ESPARZA
Smoke Detectors 1/20/2026 Approved MISAEL ESPARZA