2532 1/4-1/2 E GANAHL ST 90033

Certificate Information: 2532 1/4-1/2 E GANAHL ST 90033

Application / Permit
24010-10000-05052
Plan Check / Job No.
B24LA35284
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN***PROPOSED 2 ACCESSORY DWELLING UNITS PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 9/10/2025
Issuing Office
Current Status
CofO Issued on 3/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 SINA KHOSRAVI
Corrections Issued 12/17/2024 SINA KHOSRAVI
Quality Review Completed 12/19/2024 GARO TELMI
Applicant returned to address corrections 7/3/2025 SINA KHOSRAVI
Applicant returned to address corrections 7/24/2025 SINA KHOSRAVI
Plan Check Approved 9/2/2025 SINA KHOSRAVI
Issued 9/10/2025 APPLICANT
CofO in Progress 3/20/2026 ALIZAH MAYAGOITIA
CofO Issued 3/21/2026 DEROLD HAUFF
Permit Finaled 3/21/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/31/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/7/2025 WALLIE JONG
Sewer availability Cleared 1/7/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 2/6/2025 WALLIE JONG
GPI Written Notices Cleared 9/2/2025 SINA KHOSRAVI
Grading Pre-Inspection Cleared 9/2/2025 SINA KHOSRAVI

Contact Information

Contractor 369 Builders Inc; Lic. No.: 1125563-B       ,
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/11/2025 Partial Approval ANTHONY RAMOS
Footing/Foundation/Slab 9/22/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/2/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 11/19/2025 Approved ALIZAH MAYAGOITIA
Deputy Wood Construction 11/25/2025 Conditional Approval GEM DE OCAMPO
ELECTRICAL-Rough 12/8/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/16/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 12/16/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 12/16/2025 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 12/16/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 12/18/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/18/2025 Partial Approval ALIZAH MAYAGOITIA
Insulation 1/7/2026 Approved ALIZAH MAYAGOITIA
Shower Pan 1/7/2026 Approved ALIZAH MAYAGOITIA
Drywall Nailing 1/9/2026 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 1/9/2026 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/10/2026 Corrections Issued LILIANA PORTILLO
HVAC-Final 2/10/2026 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 2/10/2026 Approved LILIANA PORTILLO
ELECTRICAL-Final 2/17/2026 Approved ALIZAH MAYAGOITIA
Final 2/17/2026 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Final 2/17/2026 Approved ALIZAH MAYAGOITIA
MERV13>=Final 2/17/2026 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 2/17/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 2/17/2026 Approved ALIZAH MAYAGOITIA
Final 3/9/2026 Corrections Issued ALIZAH MAYAGOITIA
Service/Power Release 3/9/2026 Approved ALIZAH MAYAGOITIA
Final 3/20/2026 OK to Issue CofO ALIZAH MAYAGOITIA