2762 W FYLER PL 90065

Certificate Information: 2762 W FYLER PL 90065

Application / Permit
24010-10000-05050
Plan Check / Job No.
B24LA35281
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN New ADU per LAMC 12.22A.33
Permit Issued
Issued on 3/25/2025
Issuing Office
Current Status
Issued on 3/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/9/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 FARSHAD ALIMOHAMADI
Corrections Issued 12/27/2024 MICHAEL LOPEZ
Quality Review Completed 12/27/2024 PRANITA SHAH
Applicant returned to address corrections 3/7/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/14/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 3/24/2025 FARSHAD ALIMOHAMADI
Issued 3/25/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/4/2025 TREVOR QUAN
Street Frontage Cleared 1/4/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/8/2025 TREVOR QUAN
Sewer availability Cleared 1/8/2025 TREVOR QUAN
Hydrant and Access approval Cleared 1/10/2025 LAVEON RIDER
ZA Case Cleared 1/16/2025 GEORGIA SMITH
ZA Case Cleared 1/16/2025 GEORGIA SMITH
GPI Written Notices Cleared 3/13/2025 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 3/13/2025 MICHAEL LOPEZ
Address approval Cleared 3/15/2025 TREVOR QUAN
Roof/Waste drainage to street Cleared 3/15/2025 TREVOR QUAN
Miscellaneous Cleared 3/20/2025 ALBERT TAM

Contact Information

Contractor 369 Builders Inc; Lic. No.: 1125563-B       ,
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009
Geologist Triebold,, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 6/9/2026    Time Frame: 11-1
Footing/Foundation/Slab 6/9/2026    Time Frame: 11-1
BUILDING-Rough-Frame 6/9/2026    Time Frame: 11-1
MERV13>=Rough 6/9/2026    Time Frame: 11-1
Smoke Detectors 6/9/2026    Time Frame: 11-1
Service/Power Release 6/9/2026    Time Frame: 11-1
MERV13>=Final 6/9/2026    Time Frame: 11-1
SGSOV-Seismic Gas S/O Valve 6/9/2026    Time Frame: 11-1
Verify Sprinkler Sign Off 6/9/2026    Time Frame: 11-1

Inspection Request History

Footing/Foundation/Slab 4/29/2025 Partial Approval DAVID WILLIAMS
Deputy Reinf. Concrete 5/1/2025 Conditional Approval REGINA MENDEZ
Footing/Foundation/Slab 5/30/2025 Partial Approval DAVID WILLIAMS
BUILDING-Rough-Frame 6/9/2025 Partial Approval DAVID WILLIAMS
PLUMBING-Rough 6/9/2025 Partial Inspection DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 6/11/2025 Approved LILIANA PORTILLO
Insulation 6/11/2025 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Partial Approval LILIANA PORTILLO
Verify Sprinkler Sign Off 6/13/2025 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/11/2025 Approved JEFFREY MEAD
HVAC-Rough 7/11/2025 Approved JEFFREY MEAD
PLUMBING-Rough 7/11/2025 Approved JEFFREY MEAD
ELECTRICAL-Rough 7/24/2025 Approved DAVID WILLIAMS
Wood Frame 7/24/2025 Approved DAVID WILLIAMS
Insulation 7/31/2025 Approved GEM DE OCAMPO
Interior/Exterior Lathing 7/31/2025 Approved GEM DE OCAMPO
Interior/Exterior Lathing 8/4/2025 Approved GEM DE OCAMPO
Shower Pan 8/4/2025 Approved GEM DE OCAMPO
Drywall Nailing 8/8/2025 Approved JOSH MEISTER
Underground Mechanical 5/20/2026 Partial Approval RONNIE MEDINA
ELECTRICAL-Final 5/29/2026 Approved ROY SPAULDING
HVAC-Final 5/29/2026 Approved ROY SPAULDING
PLUMBING-Final 5/29/2026 Approved ROY SPAULDING